Hiren Sevak
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
I would like to highlight requirement out lined in ASME B 31.3 as below.
# Refer Para 341.3.1(a)
“For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment”
# Refer Note (11) in “NOTES FOR APPENDIX A TABLES “ (Pg 147 – 2010 edition)
“For use under this Code, radiography shall be performed after heat treatment”
This note(11) pointing P3, P4, P5A, P5B, P9A & P9B materials only as per table A-1.
And of course, Re-PWHT shall be carried out if any repair comes, in case of RT after PWHT.
Regds/Jignesh
Dear Jignesh Sir,
As per metallurgy point of view we can done PWHT cycle only one time if we go for second time we have to qualify Repair WPS. Pls reply me for any suggestion.
Thanks,
HHS
Hiren Sevak
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
Dear Experts,
Piping Code : ASME B 31.1, Power Plant Piping, (P No.5A,11,12,15, 91 etc pipes) & ASME Sectin I
Contractor is doing piping fabrication stages in following manner,
Preheating & Welding of Piping joints then Post heating, then PWHT & then finally RT.
Contractor is arguing, RT is taken after PWHT to reveal the defects causing due to delayed cracking.
My question
If RT repair is done for particular joint after PWHT then is it compulsory to perform PWHT again for particular joint ? if yes then please mention the clause of code.
Thanks & Regards
Hiren Sevak
--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to mailto:materials-welding%2Bunsu...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
From: material...@googlegroups.com [mailto:material...@googlegroups.com] On Behalf Of Siva
Subject: Re: [MW:15269] Repair after PWHT - B 31.1
PWHT shall be done after weld repair. So my understanding is, to find weld repairs, we need to perform NDT before PWHT. I have seen in my experience, normally, NDT will be done prior to and after PWHT also(i.e., twice on that joint).
If NDT done only after PWHT, found any defects, then after weld repair, again should perform PWHT, which might effect mechanical properties.
On Mon, Sep 10, 2012 at 9:10 AM, sevak hiren <hirens...@gmail.com> wrote:
Dear Experts,
Piping Code : ASME B 31.1, Power Plant Piping, (P No.5A,11,12,15, 91 etc pipes) & ASME Sectin I
Contractor is doing piping fabrication stages in following manner,
Preheating & Welding of Piping joints then Post heating, then PWHT & then finally RT.
Contractor is arguing, RT is taken after PWHT to reveal the defects causing due to delayed cracking.
My question
If RT repair is done for particular joint after PWHT then is it compulsory to perform PWHT again for particular joint ? if yes then please mention the clause of code.
Thanks & Regards
Hiren Sevak
--
To post to this group, send email to material...@googlegroups.com
| Follow Rediff Deal ho jaye! to get exciting offers in your city everyday. |
Hiren Sevak
For repair carried out after pwht than pwht is mandatory after repair if service requirement.
If as per code than exemption clause shall be applicable based on depth of repair.