Repair after PWHT - B 31.1

1,623 views
Skip to first unread message

sevak hiren

unread,
Sep 10, 2012, 2:10:11 AM9/10/12
to material...@googlegroups.com
Dear Experts,

Piping Code : ASME B 31.1, Power Plant Piping, (P No.5A,11,12,15, 91 etc pipes) & ASME Sectin I

Contractor is doing piping fabrication stages in following manner,

Preheating & Welding of Piping joints then Post heating, then PWHT & then finally RT.

Contractor is arguing, RT is taken after PWHT  to reveal the defects causing due to delayed cracking.

My question

If RT repair is done for particular joint after PWHT then is it compulsory to perform PWHT again for particular joint ? if yes then please mention the clause of code.

Thanks & Regards

Hiren Sevak






Siva

unread,
Sep 11, 2012, 2:49:05 AM9/11/12
to material...@googlegroups.com
PWHT shall be done after weld repair. So my understanding is, to find weld repairs, we need to perform NDT before PWHT. I have seen in my experience, normally, NDT will be done prior to and after PWHT also(i.e., twice on that joint).
If NDT done only after PWHT, found any defects, then after weld repair, again should perform PWHT, which might effect mechanical properties.



Hiren Sevak






--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 



--
Regards,
G.Sivalingam., BE.,
Quality Control Inspector - Welding,
SAS Project, Abu Dhabi, UAE.

Desai Jignesh (Mumbai - Piping)

unread,
Sep 12, 2012, 12:01:27 AM9/12/12
to material...@googlegroups.com

I would like to highlight requirement out lined in ASME B 31.3 as below.

 

# Refer Para 341.3.1(a)

 “For P-Nos. 3, 4, and 5 materials, examination shall be performed after completion of any heat treatment”

 

# Refer Note (11) in “NOTES FOR APPENDIX A TABLES “ (Pg 147 – 2010 edition)

“For use under this Code, radiography shall be performed after heat treatment”

This note(11) pointing P3, P4, P5A, P5B, P9A & P9B materials only as per table A-1.

 

And of course, Re-PWHT shall be carried out if any repair comes, in case of RT after PWHT.

 

Regds/Jignesh

hemant

unread,
Sep 13, 2012, 12:17:52 AM9/13/12
to material...@googlegroups.com

Dear Jignesh Sir,

As per metallurgy point of view we can done PWHT cycle only one time if we go for second time we have to qualify Repair WPS.  Pls reply me for any suggestion.

 

Thanks,

HHS

Biplab Pal

unread,
Sep 13, 2012, 2:28:27 AM9/13/12
to material...@googlegroups.com
Dear Hiren Sevak,
 
I have a very simple opinion.
Your WPS specifies about PWHT, if yes it is essential variable for Production Welding.
It is required by code/std./spec. that we sould perform RT after completion of welding. If PWHT is not done, i think the weld is not complete according to WPS. So you can not perform RT before completion of welding of any joint.



On Mon, Sep 10, 2012 at 9:10 AM, sevak hiren <hirens...@gmail.com> wrote:


Hiren Sevak






--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to materials-weld...@googlegroups.com
For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 



--
Thanks & Regards
Biplab Pal
Mechanical Inspector (PMT)
YASREF Project

E-mail:   bipla...@gmail.com
 
Information in this email and any attachments is confidential and intended solely for the use of the individual(s) to whom it is addressed or otherwise directed. Please note that any views or opinions presented in this email are solely those of the author and do not necessarily represent those of the Company. Finally, the recipient should check this email and any attachments for the presence of viruses. Myself accepts no liability for any damage caused by any virus transmitted by this email.
 

Dindo

unread,
Sep 13, 2012, 9:02:43 AM9/13/12
to material...@googlegroups.com
First thing is you have to do your due dilligence by doing NDT prior to sending for PWHT, so that you wont get caught unaware of the repair before it goes to the oven.
 
Second thing is if there is a repair after PWHT, then you have to cut out the whole weld and redo the weld.

PRAMODH NAIR

unread,
Sep 15, 2012, 8:25:03 AM9/15/12
to material...@googlegroups.com
Required PQR after secopnd time PWHT. Because its affect the mechanical properties.
 
Regards
Pramodh

From: Siva <siva7...@yahoo.com>
To: material...@googlegroups.com
Sent: Tuesday, September 11, 2012 12:19 PM
Subject: Re: [MW:15269] Repair after PWHT - B 31.1

PWHT shall be done after weld repair. So my understanding is, to find weld repairs, we need to perform NDT before PWHT. I have seen in my experience, normally, NDT will be done prior to and after PWHT also(i.e., twice on that joint).
If NDT done only after PWHT, found any defects, then after weld repair, again should perform PWHT, which might effect mechanical properties.

On Mon, Sep 10, 2012 at 9:10 AM, sevak hiren <hirens...@gmail.com> wrote:
Dear Experts,

Piping Code : ASME B 31.1, Power Plant Piping, (P No.5A,11,12,15, 91 etc pipes) & ASME Sectin I

Contractor is doing piping fabrication stages in following manner,

Preheating & Welding of Piping joints then Post heating, then PWHT & then finally RT.

Contractor is arguing, RT is taken after PWHT  to reveal the defects causing due to delayed cracking.

My question

If RT repair is done for particular joint after PWHT then is it compulsory to perform PWHT again for particular joint ? if yes then please mention the clause of code.

Thanks & Regards


Hiren Sevak






--
To post to this group, send email to material...@googlegroups.com
To unsubscribe from this group, send email to mailto:materials-welding%2Bunsu...@googlegroups.com

For more options, visit this group's bolg at http://materials-welding.blogspot.com/
http://www.linkedin.com/groups/MaterialsWelding-122787?home=&gid=122787&trk=anet_ug_hm
 
The views expressed/exchnaged in this group are members personel views and meant for educational purposes only, Users must take their own decisions w.r.t. applicable code/standard/contract documents.
 
 



--
Regards,
G.Sivalingam., BE.,
Quality Control Inspector - Welding,
SAS Project, Abu Dhabi, UAE.

sachin sankhe

unread,
Sep 16, 2012, 1:00:34 PM9/16/12
to material...@googlegroups.com
If PWHT is process requirement (Sau caustic) then any repair on job after PWHT calls for re-PWHT(Of course you need to qualify welding procedure also)
However if PWHT requirement is due to base metal thk then depends if repair depth  after PWHT is less than thk that require PWHT as per code then i feel PWHT may not be required(But u need to qualify the welding procedure for this also)

Regards
Sachin.Sankhe

Subject: Re: [MW:15269] Repair after PWHT - B 31.1

PWHT shall be done after weld repair. So my understanding is, to find weld repairs, we need to perform NDT before PWHT. I have seen in my experience, normally, NDT will be done prior to and after PWHT also(i.e., twice on that joint).
If NDT done only after PWHT, found any defects, then after weld repair, again should perform PWHT, which might effect mechanical properties.

On Mon, Sep 10, 2012 at 9:10 AM, sevak hiren <hirens...@gmail.com> wrote:

Dear Experts,

Piping Code : ASME B 31.1, Power Plant Piping, (P No.5A,11,12,15, 91 etc pipes) & ASME Sectin I

Contractor is doing piping fabrication stages in following manner,

Preheating & Welding of Piping joints then Post heating, then PWHT & then finally RT.

Contractor is arguing, RT is taken after PWHT  to reveal the defects causing due to delayed cracking.

My question

If RT repair is done for particular joint after PWHT then is it compulsory to perform PWHT again for particular joint ? if yes then please mention the clause of code.

Thanks & Regards

Hiren Sevak




--

To post to this group, send email to material...@googlegroups.com



Follow Rediff Deal ho jaye! to get exciting offers in your city everyday.

Muhammed Ibrahim PK

unread,
Sep 17, 2012, 2:01:40 AM9/17/12
to material...@googlegroups.com
PWHT shall be done after repair. To avoid this issue better to perform RT before PWHT also.

Thanks & Regards
Muhammed Ibrahim PK





Hiren Sevak






sabi sabi

unread,
Sep 17, 2012, 5:53:19 PM9/17/12
to material...@googlegroups.com
Dear gents,
 
Case-1: Normal practice
1.welding (with/without pre heat & post heat)
2.RT
3.Clear repair + RT
3.PWHT
4.RT
 
Case-2: Some agents are doing (with confidence of worker & Did not get a time fot RT)
1.welding (with/without pre heat & post heat)
2.PWHT
3.RT
4.Clear repair (with/without RT)
5.PWHT
6.RT
 
Solution of case-2: There is no problem for twice PWHT. It will not affect any meterial properties.
 
That is the reason, we are taking hardness test to meet requirement. Only time will take more.
 
Regards,
sabi

Muhammed Ibrahim PK

unread,
Sep 19, 2012, 4:06:43 AM9/19/12
to material...@googlegroups.com
Double PWHT will reduce tensile strength.

Thanks & Regards
Muhammed Ibrahim PK



Sanjay Yadav

unread,
Sep 27, 2012, 7:01:08 AM9/27/12
to material...@googlegroups.com

For repair carried out after pwht than pwht is mandatory after repair if service requirement.
If as per code than exemption clause shall be applicable based on depth of repair.

Reply all
Reply to author
Forward
0 new messages