Dear experts,
we generally carryout hydro test with 1.5 time design pressure and holding time of 60 minutes with two pressure gauges. one at inlet and another at top vent.
can any one provide me from which standard and clause we use this procedure. particularity for 60 minutes holding time i need reference clause/standard
Note: this is for air receiver / Pressure vessel.
--
Thanks and Regards, ?
Mohammed Ghani,
CSWIP 3.1 / BGAS L-2 / ISO 9001:2008 QMS LA.
Mechanical Inspector,
BUREAU VERITAS.
ü Please consider the environment before printing this email.
"Be the change you wish to see in the world"
---Mahatma Gandhi---