Fwd: Summerhall - road and footway resurfacing, traffic signals renewal

3 views
Skip to first unread message

MarchmontSciennes Community Council

unread,
Jan 12, 2026, 7:24:22 AMJan 12
to marchmontandsciennes


---------- Forwarded message ---------
From: Alan Parkinson <Alan.Pa...@edinburgh.gov.uk>
Date: Fri, 9 Jan 2026 at 12:19
Subject: Summerhall - road and footway resurfacing, traffic signals renewal
To: marchmontscien...@googlemail.com <marchmontscien...@googlemail.com>, ad...@sccedinburgh.org.uk <ad...@sccedinburgh.org.uk>, secr...@grangeprestonfieldcc.org.uk <secr...@grangeprestonfieldcc.org.uk>


Good afternoon,

 

I am writing to advise you of upcoming roadworks in the Newington area of the city that will commence on 26 January 2026 and take 16 weeks to complete. The Contractor for the works is J H Civil Engineering Ltd. A location plan is enclosed for your information.

 

The works comprise the following:

  • Road and partial footway resurfacing of Hope Park Crescent and Summerhall between Buccleuch Terrace and Summerhall Square
  • Renewal of traffic signals infrastructure at the junction of Hope Park Cresent, Hope Park Terrace, Summerhall, and Melville Drive
  • Improved pedestrian facilities comprising widened footpaths, continuous footways, shorter crossing points and updated vehicle crossovers
  • Provision of permanent segregated cycle lanes
  • Removal of street clutter

 

The works will be split into various phases, with the footway and traffic signal work being completed first, followed by the road resurfacing.

 

  • Footway and traffic signals work will be undertaken between 0700 hrs and 1900 hrs Monday to Friday.

 

  • Road resurfacing work will be undertaken overnight between 1900 hrs and 0600 hrs Monday to Friday, with noise restrictions in place after 2300 hrs. Diversion routes will be in operation to facilitate this work but will be removed during the day. This phase is expected to take no more than seven nights to complete.

 

A letter informing residents and businesses on affected streets of the works will be distributed next week. They will be kept informed throughout the works by on-street signage, letters and personal visits from staff or contractors.

 

Regards,

Alan Parkinson

Engineer

t: 07857 664925

e: alan.pa...@edinburgh.gov.uk

 

The City of Edinburgh Council

Transport Contracts and Design | Roads and Infrastructure | Operational Services | Place

G.5 | Waverley Court | 4 East Market Street | Edinburgh | EH8 8BG

 

**********************************************************************
This email and files transmitted with it are confidential and are intended for the sole use of the individual or organisation to whom they are addressed.
If you have received this eMail in error please notify the sender immediately and delete it without using, copying, storing, forwarding or disclosing its contents to any other person.
The Council has endeavoured to scan this eMail message and attachments for computer viruses and will not be liable for any losses incurred by the recipient.
**********************************************************************
TCD-000184-2-01A (I 2025-12-04).pdf
Reply all
Reply to author
Forward
0 new messages