2025-04-15 Meeting Minutes
Call to order: 20:54 by Kevin
Attendees
The usual suspects
Kevin
Hong
Brandon
Richard
Ed
Michael
Curator Hours 2025-04-15
Day use visitor
Potential Member visited
Open Project Night (18:30, Fri 2025-04-11)
Brandon L. hosted.
No memories
Open House Party (Sat 2025-04-12 18:00)
Kevin is Hosting
Nothing of note happened
Open Project Night (18:30, Fri 2025-04-18)
Brandon is hosting
Open Welding Practice (Sat 2025-04-19 17:00)
Machines
Big Blue
Michael’s
Space MIG
Richard’s Flux Core
On loan on the pallet rack
Processes
Likely to leave machines on “recommended settings” and have the students figure out setting information later
Most likely to recommend the gasless processes unless somebody asks
Stick
Flux Core
Could run the gassy processes
Tig
Mig
Necessary Materials
Samples
Square Tubing / Round Tubing
Joints!
“X” Crucible
3 suppliers near us:
IMS
Patton’s
Unicorn
Mig wire
5lb spool, unspecified size
Host
Kevin is Hosting
Visiting the land of dancing unicorns event (Sat 2025-04-19 08:00)
Meet at MAG Lab
Drive to the Unicorn Metals
Brandon L. (CTO)
Still working on the outdoor awning lights
Need to be wired
Water filter needs to be maintained
Bought new RFID keychains (might not break so often)
Now Offering “No Questions asked” Exchange of Blue “H” Mark keychains to new black RFID keychains
Paper towel dispenser showed up / got installed
Hong Q (Treasurer)
Membership payment from contacted member resumed
Taxes in progress
Dolly wheel is still flat
New wheel purchased / needs to be installed
Old bottle of slime to try on dolly wheel
Outdoor lightbulb needs replacement
Old bulb works… sometimes.
New bulb works… never.
Now shopping for LED fixtures
Spring cleaning should be in the works
Upholstery cleaner at MAG Lab
To enforce the table clean-up and purg policy
Something about a mill
75” from the wall to the gearbox on the lathe
75” is the largest dimension on the mill
The mill will not fit
Motion to end: Brandon, Kevin
Meeting ended: 21:35 by Kevin