LHCb's Logbook yet again has the info. Collisions planned this week, but with beams at 450GeV each.

--

- 08:00 Dump tests with beam
- 12:00 Short access (1 hour machine, 2 hours for UXs)
        start pre-cycling machine

Afternoon/evening:

- 15:00 15 min of TI2 TED shots for ALICE, 30 min of
        inject/circ and dump for RF checks
- 16:00 MPS BLM tests, including collimator moves
- 24:00 Aperture/kick response

Notes: - goal of the week: STABLE BEAMs, make collisions at 900 GeV