An additional two answers from Alain on questions asked at the onsite meeting of 27th Nov.
 
See below.
 
Cheers,

 
_________________________
David P. Mennier
Ottawa

 

From: Alain.M...@ottawa.ca
To: men...@hotmail.com
CC: Taffy...@ottawa.ca; peter...@ottawa.ca; mary.di...@ottawa.ca; Kimberl...@ottawa.ca
Subject: On outstanding questions
Date: Tue, 4 Dec 2012 20:56:54 +0000

Dear Mr. Mennier,

 

I still owed you answers on two outstanding questions from our on-site meeting last week, please convey these to your neighbours:

 

Piped infrastructure:

There is no piped infrastructure (water, wastewater, stormwater) under this lane.

 

Compensation:

There is no compensation available to owners for the removal of encroachments from the lane.

 

In addition, I would like to speak with you by phone, if possible this week, regarding the planned meeting of December 20th.

 

Thank you,

 

 

Alain Miguelez, mcip, rpp

Program Manager, Zoning, Intensification and Neighbourhoods |  Gestionnaire de programme, Zonage, Densification et Quartiers

Planning and Growth Management Dept. | Service de l’Urbanisme et de la Gestion de la croissance

City of Ottawa | Ville d’Ottawa

) 613.580.2424 +27617