Crews are working to maintain the job site and complete work where possible while wet and blustery weather continues. As we head into the holidays, utility and street work will continue but expect work to stop Dec. 25-26 and Jan. 1 for Christmas and the New Year holidays.
Upcoming Construction
 This week (December 15-19)
- Temporary sidewalk work at 10th Ave NE (Work Zone 3)
- Cement pouring for roadway concrete at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), and at 15th Ave NE (Work Zone 4)
- Underground electrical utility installation at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), 15th Ave NE (Work Zone 4), 20th Ave NE (Work Zone 5), and 23rd Ave NE (Work Zone 6)
Week of December 22
-
No work December 25-26 for the Christmas holiday
- Cement pouring for roadway concrete at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), and at 15th Ave NE (Work Zone 4)
- Underground electrical utility installation at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), 15th Ave NE (Work Zone 4), 20th Ave NE (Work Zone 5), and 23rd Ave NE (Work Zone 6)
Week of December 29
- No work January 1 for the New Year holiday
- Cement pouring for roadway concrete at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), and at 15th Ave NE (Work Zone 4)
- Underground electrical utility installation at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), 15th Ave NE (Work Zone 4), 20th Ave NE (Work Zone 5), and 23rd Ave NE (Work Zone 6)
Week of January 5
- Cement pouring for roadway concrete at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), and at 15th Ave NE (Work Zone 4)
- Underground electrical utility installation at 8th Ave NE (Work Zone 2), 10th Ave NE (Work Zone 3), 15th Ave NE (Work Zone 4), 20th Ave NE (Work Zone 5) and 23rd Ave NE (Work Zone 6)
What to Expect During Construction
- Typical weekday working hours of 7 AM – 5 PM
- Lane shifts, closures, temporary detours, and short delays in active work zones. Flaggers will direct traffic as needed.
- Steel plates on roadway which can be slippery. Please be alert when traveling through the project area.
- Barrier-separated paths for people walking, biking, and rolling through the construction area
- Parking restrictions near the project area for material and equipment storage
- Noise, dust, and vibrations during active construction
- Potential impacts to bus stops. Please visit King County Metro’s Service Advisories page for current route and stop information.
Roosevelt Way NE and 10th Ave NE Closures
Closures continue at the intersection of Roosevelt Way NE/NE 125th St and 10th Ave NE. See map below for detour routes and please be alert for signage and flaggers when traveling through the area.
Other Projects in the Area
Sound Transit Pinehurst Station
Continued closure of eastbound NE 130th St. Visit the Pinehurst Station website for construction updates.
City of Shoreline 145th Street Corridor Project |
The City of Shoreline is building improvements for the SR 523 (N/NE 145th Street) and Interstate 5 (I-5) interchange including NE 145th Street between 5th Avenue NE and the on- and off-ramps on the west side of I-5. Visit their website for construction updates.
Photo of the Week
 Crews measuring electrical conduits
Questions or want more information?
|