Final release plan

15 views
Skip to first unread message

Christian Kaltepoth

unread,
Nov 21, 2019, 11:52:55 AM11/21/19
to MVC 1.0 Users, jsr371-...@googlegroups.com, krazo developer discussions
Hi all,

as we are getting closer to our final release, I would like to share the concrete steps planned of the next days/weeks. Just to keep everyone updated. :-)
  • Release 1.0.0-RC1 of the API and TCK
  • Update the Eclipse Krazo dependencies to these RC versions
  • Create CQs for the new dependencies + get approval for the IP Log / release plan
  • Release Krazo 1.0.0-RC1
  • Send all material including the RC1 versions to the JCP for approval
  • Wait for the JCP final release approval
  • Publish 1.0.0 of the API and TCK
  • Update Krazo dependencies (my hope is that updating from 1.0.0-RC1 to 1.0.0 won't require additional paperwork)
  • Stage Krazo 1.0.0 and start the Eclipse release review
  • Publish Krazo 1.0.0 after we get EF approval 
Looks like we have some work to do. :-)

Christian


--

Daniel Dias Dos Santos

unread,
Nov 21, 2019, 12:52:12 PM11/21/19
to jsr371...@googlegroups.com, jsr371-...@googlegroups.com, krazo developer discussions
Very good . :  ) 
--
Daniel Dias dos Santos
Java Developer
SouJava & JCP Member
Linkedin: www.linkedin.com/in/danieldiasjava


--
You received this message because you are subscribed to the Google Groups "MVC 1.0 Users Mailing List" group.
To unsubscribe from this group and stop receiving emails from it, send an email to jsr371-users...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/jsr371-users/CAEXeC6x-9ZOW5VVoqxcAN7jTtM-DC1p8RaN042Yt9u8pp4-pZw%40mail.gmail.com.
Reply all
Reply to author
Forward
0 new messages