Delay next LTS baseline by 2 weeks for end of year break?

30 views
Skip to first unread message

Mark Waite

unread,
Oct 21, 2026, 7:24:18 AM (18 hours ago) Oct 21
to jenkinsci-dev
The next LTS baseline is scheduled for selection on Nov 11, 2026, with a release planned for Dec 23, 2026.

I propose delaying both the baseline selection and the release date by two weeks to accommodate our typical two week break at the end of the calendar year.  We would choose the baseline on Nov 25, 2026 and release the first version of the next LTS line on Jan 6, 2027.

Mark Waite

Kris Stern

unread,
Oct 21, 2026, 9:51:01 AM (16 hours ago) Oct 21
to jenkinsci-dev
Hi Mark,

+1 from me

Best,
Kris


From: jenkin...@googlegroups.com <jenkin...@googlegroups.com> on behalf of Mark Waite <mark.ea...@gmail.com>
Sent: 21 October 2026 19:23
To: jenkinsci-dev <jenkin...@googlegroups.com>
Subject: [jenkinsci-dev] Delay next LTS baseline by 2 weeks for end of year break?
 
The next LTS baseline is scheduled for selection on Nov 11, 2026, with a release planned for Dec 23, 2026.

I propose delaying both the baseline selection and the release date by two weeks to accommodate our typical two week break at the end of the calendar year.  We would choose the baseline on Nov 25, 2026 and release the first version of the next LTS line on Jan 6, 2027.

Mark Waite

--
You received this message because you are subscribed to the Google Groups "Jenkins Developers" group.
To unsubscribe from this group and stop receiving emails from it, send an email to jenkinsci-de...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/jenkinsci-dev/CAO49JtHFESfEstcW57K7gCuTaCrDi7ytppry0nSAwXEV4q9ZHQ%40mail.gmail.com.

Tim Jacomb

unread,
Oct 21, 2026, 9:54:23 AM (16 hours ago) Oct 21
to jenkin...@googlegroups.com

Ullrich Hafner

unread,
Oct 21, 2026, 2:42:47 PM (11 hours ago) Oct 21
to Jenkins Developers

Michael Nazzareno Trimarchi

unread,
Oct 21, 2026, 3:25:22 PM (10 hours ago) Oct 21
to jenkin...@googlegroups.com
+1


Michael


Michael Nazzareno Trimarchi
Co-Founder & Chief Executive Officer
M. +39 347 913 2170
mic...@amarulasolutions.com
__________________________________

Amarula Solutions BV
Joop Geesinkweg 125, 1114 AB, Amsterdam, NL
T. +31 (0)85 111 9172
in...@amarulasolutions.com
www.amarulasolutions.com

Alexander Brandes

unread,
Oct 21, 2026, 3:25:47 PM (10 hours ago) Oct 21
to Jenkins Developers
+1

Daniel Beck

unread,
Oct 21, 2026, 3:55:01 PM (10 hours ago) Oct 21
to jenkin...@googlegroups.com
On Wed, Oct 21, 2026 at 1:24 PM Mark Waite <mark.ea...@gmail.com> wrote:
I propose delaying both the baseline selection and the release date by two weeks to accommodate our typical two week break at the end of the calendar year.  We would choose the baseline on Nov 25, 2026 and release the first version of the next LTS line on Jan 6, 2027.

What's the RC date in this updated schedule?

CONFIDENTIALITY NOTICE: This email and any attachments contain confidential and proprietary information of CloudBees intended only for the named recipient(s). Unauthorized use or distribution is prohibited. If you received this in error, please notify the sender and delete this email.

Mark Waite

unread,
Oct 21, 2026, 4:30:22 PM (9 hours ago) Oct 21
to jenkinsci-dev
I placed it on the Jenkins calendar two weeks after the baseline is selected.

--
You received this message because you are subscribed to the Google Groups "Jenkins Developers" group.
To unsubscribe from this group and stop receiving emails from it, send an email to jenkinsci-de...@googlegroups.com.
Reply all
Reply to author
Forward
0 new messages