<JAM MOM 100313.jpg>
Dear Sir,Greetings.Kindly let us about power connection.In the last meeting you have picked 20/03/2013 as the day you will let us know about power connection. Also as per your commitment all the common area will be liveable condition ready by 31/03/2013. But so far we don't see any significant progress. Kindly update on that too.Regards,MuralirajaDear Sir,Thanks for attending the meeting as promised & answering our queries.Herewith I have attached Minutes Of Meeting -key points discussed during the meeting- signed by Mr. Thomas on behalf of Jain Housing.We hope all our issues will be sorted out soon as promised.Kindly let us know when we can schedule next meeting.Regards,On Behalf of Jains Alpine Meadows Residents:Block 1-11Muraliraja<JAM MOM 100313.jpg>
--
I agreed..Bala1-FDOn Mon, Mar 25, 2013 at 7:54 PM, Akv <akvela...@yahoo.com> wrote:
Dear All,
Shall we meet on coming Sunday 31.03.2013 for discussions to take stock of current situation & to formulate further course of action.
Regards,
A K Velayutham 7 TH
From: manickam venkatesan
Sent: 25-03-2013 PM 03:23
To: jains-alpine-mead...@googlegroups.com
Subject: Re: Re: [Jains Alpine Meadows, Thiruneermalai:85] Jains AlpineMeadows-MOM Dt 10/03/13
--
Regards
Bala
--
You received this message because you are subscribed to the Google Groups "Jains Alpine Meadows, Thiruneermalai" group.
To unsubscribe from this group and stop receiving emails from it, send an email to jains-alpine-meadows-th...@googlegroups.com.
To post to this group, send email to jains-alpine-mead...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
Hi Neel: Pl. check the proposed date of meeting, the date should be on or before 6th April 2013 ?
Rgds/Radhakrishnan KK
Block 6/TH
this saturday will be fine, we go directly without apponitment
|
| Dear Friends, Request anyone who is staying right now in the premises pls verify with Thomas and check these letters(TNEB & CMDA) are available with site crew. Throw more light on the facts/documents available with Thomas. Most of us (who are yet to swift from our current location to the new houses) have already informed the house that we are vacating our rental house by end of MAY 2013. If suppose we do not get the power and if we could not come in to the new house, it will be a havoc! I do not know what is our say if this could not happen.This is really SERIOUS ! Thanks and regards, AK Velayutham - 7 TH 9500056920 --- On Tue, 4/16/13, saravanan venkatesan <sarava...@gmail.com> wrote: |
| Dear Murali Raja, Thanks for the initiative. CEO also send in his reply that they will complete all the works. But the ground reality is that there is no developments happening at the site. kindly inform CEO on the site status & request him to put pressure onto site team to carryout cabling works. we all need to put pressure to see the works are completed by this month end. lets not give room to builder to come up with another postponement of the date of completion. Thanks for the update Kannan.... Thanks, AK Velayutham 7-TH |