Om Sugars Plans To Set Up
Om Sugars Limited plans to set up a Molasses based Distillery having capacity of 30 KLPD along with 1.5 MW Co-Generation Power Plant (Bagasse/ Biogass/ /Biomass ) at Jainapur Village & Post, Chikodi Taluk in Belagavi District, Karnataka.
Distillery : 30 KLPD
(RS/ENA/Ethanol)
=====================
Co-Generation Power Plant : 1.5 MW
( Fuel : Bagasse/ Biogass/ /Biomass)
=====================
CO2 Plant : 22.8 TPD
Total Working Days in a year : 270 days
Project Cost : Rs.47.40 Crores
Location : Jainapur Village & Post, Chikodi Taluk
Belagavi District, Karnataka
As on November 20, 2015 : The Project is under Planning Stage.
The unit would come up in 20 Acres of Land .
Out of this about 33% of the area will be developed as Green Belt.
********************************************************
Note : The company is presently operating a Sugar Plant of capacity 2500 TCD & 4 MW Co-Genpower Plant and the existing Pant Ste is located on land admeasuring 48 acres in cane rich belt.
***********************************
IMPORTANT: As per the the discussion we had
on 06.11.2015 with Om Sugars Limited
the Project is under Panning Stage.
The company is now waiting for Environmental clearances .
The Project is
Scheduled to be Completed in
15-18 Months from the date of commencement of the project work.
=======================================
So, this is the RIGHT TIME to contact and Follow Up at following address
to obtain the detailed Enquiry of each product in time and to
submit your quotation subsequently.
The Main Scope of Supply includes:
Boiler : 10 TPH - 1 No.
Fuel (as avialable) : Bagasse/ Biogass/ /Biomass
Fuel Consumption : Bagasse : 33.3 TPD /
Biogass : 470 m3/hr/
Biomass : 56 TPD
Heat Exchanger, Air Pre-Heater/ Economiser
===============================
Raw Materials :
Molasses : 120 TPD
===============================
Air Pollution Control Equipment :
Bag Filter
To control the particulate emissions from Coal Fired boiler will be controlled by Bag Filter and emissions will be dispersed through Stack of suitable Height. .
Steam generated from the boilers and will be utilized in the generation of
1.5 MW Power and will also be used for Boiler feed water heating and Distillery.
Flue gases after super heating the steam will pass through Economizer where they will Pre-Heat the boiler Feed water before it enters the boiler drum. After Economizer, flue will pass through Air Pre-Heaters where they will heat the air which will be fed to the boiler furnace for burning the fuel.
************************************************************************
Steam turbine
with Step down transformer & synchronization Ash handling system
Air Cooled Condenser
Power plant stack
Single Chimney
Fuel system
Cooling Tower
Pumps
*************************************
Cooled Condenser :
Use of Air Cooled Condenser to be used to reduce water consumption.
All the Conveyors will be covered with GI sheets to prevent the fugitive dust emission into the atmosphere.
DG set :
will be installed
for emergency power Back-up during power failure.
Water Treatment Plant
Oxidisation Chamber, Pressure Sand Filter / IRF, DM Plant,
Tube Settler
Pumps Valves, Custom Pipeline Work.
Total water requirement for the above project will be
400 KLD will be sourced from and same will be met from the Doodhganga River..
************************************
Effluent Treatment Plant :
The Boiler blow down & DM Plant & Softener regeneration water will be treated in a neutralization tank and after treatment it will be mixed with CT Blow down.
All these treated effluent streams will be stored in a Central Monitoring Basin (CMB). The treated effluent will be used for greenbelt development/dust suppression / ash conditioning. The scrubbed water from CO2 Scrubber will be consumed in the Fermentation section.
The effluent will be used for greenbelt development within the plant premises after ensuring the compliance with CPCB/SPCB standards.
Spent wash from molasses based distillery will be treated in biomethanisation, concentrated in Multiple Effect Evaporators (MEE) followed by Bio-composting.
*************************************
Other Equipments:
Material Handling Equipment : Conveyor, Hydraulic Equipment/Cranes,
DG Set, Air Compressor. DC/VFD Drive, Gear Box, Insulation, Valves, Pipes & Tubes, Cables, Automatic Weighing Machines for Bulk & Liquid Materials. Straight Line Steam Tunnel, Pneumatic Piston Filler, Pressure Filler,Storage Tank, Cooling Tower/ Plant, Air Conditioning Plant, Complete Laboratory Equipments etc
Fire Fighting System shall be as per the TAC Norms and cover all areas where alcohol is produced, handled and stored.
Provision of Foam System for Fire Fighting to control fire from the alcohol storage tank.
Green Belt Development plan in 33 % area and a scheme for Rainwater Harvesting have to be put in place.
Scope Of Entire Civil & Construction Work:
Construction of Office Building, Factory Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication Storage Tank, Vessels etc. etc.
Companies/ General Industries/ Contractors/ Sub Contractors/ Manufacturers of Boiler, Material Handling Equipment , Water Treatment Plant, Effluent Treatment Plant, Air Pollution Control Equipments, Cooling Tower, Blowers, Cranes, Hydraulic Equipments, Water line Valve, Pump, Pipeline etc. related to Distillery Plant may Contact for Specified Enquiry at :
Om Sugars Limited
Classique Hts, Flat No - 203
4824/C-7 S.P. Office Road
Kolhapur Circle ,Belgaum - 590016, Karnataka, India
-----------------------------
Tel : +91-831-2433899/ 2420161
Fax :+ 91-831-2433899
Email : o...@omsugars.com / omsu...@gmail.com
Website : www.omsugars.com
*****************************
| New Projects |
FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES
Visit : http://industrialdirectoryofindia.com/FAQ
GET NEW PROJECTS INFORMATIONS ONLINE
http://www.industrialdirectoryofindia.com/download
We provide information on NEW PROJECTS such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.
with all Contact Details:
Company's Name
Address/ Phone/ Fax
Contact person's Name
E-mail Id
We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.
We make your Bidding/MARKETING/ Sub-contracting & Planning MORE EASY
GET YOUR COMPANY REGISTERED TODAY AND GET ALL PROJECTS INFORMATIONS DIRECTLY IN YOUR MAIL BOX .
Visit : http://www.industrialdirectoryofindia.com/registration
GET ALL BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX
------------------------------------------------------------------------------------------------------------
RELEASED ANNUAL ISSUE :
“NEW PROJECTS THIS WEEK”