Jaypee Cement Plans 6 MTPA Integated Cement Plant With 90 MW CPP...

228 views
Skip to first unread message

Industrial Directory Of India

unread,
Nov 30, 2011, 11:49:53 AM11/30/11
to industrialdir...@googlegroups.com
                         “New Projects This Week" 

                   RELEASED : ISSUE NOVEMBER  27 /11 

              Comprising  of  Total  62 New Project Enquiries 

  with Company's Name/ Address/ Phone/ Fax/ Contact person/E-mail 
                (Published Every Week :Electronic Issue) 
          http://www.industrialdirectoryofindia.com/download

FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES

           Visit http://industrialdirectoryofindia.com/FAQ

    (Helpline : +91-900 7158 600) 

 

      Jaypee Cement Plans 6 MTPA

Integated Cement Plant With 90 MW CPP

 

    (Update : Refer our Earlier Report Dtd. 21.05.2011)

 

Jaypee Cement Corporation Limited pans to set up setting up  a Greenfield Integrated Cement Plant having Capacity of  6.0 MTPA (3.0 MTPA each in Phase I & II), along with  Coal Based Captive Power Plant : 90 MW (30 MW in Phase I and 60 MW in Phase II)  at Bankur Village, Tehsil Chittapur, District Gulbarga in Karnataka.

 

Capacity :

Cement Plant   : 6.0 MTPA

  1. Phase I   : 3.0 MTPA 

  2. Phase II : 3.0 MTPA 

 

Captive  Power Plant :  90 MW

   (earlier it was proposed 70 MW)

  (Coal Based)

 

  1. Phase I   : 30 MW 

  2. Phase II : 60 MW 

 

 

Location :   Village Bankur, Tehsil Chittapur,
                 District Gulbarga, Karnataka

 

About Jaypee Cement’s Gulbarga Plant :

Jaypee Cement Corporation Limited (formerly M/s Zawar Cement Private Limited) : The plant will be located within the boundary limits (38 ha) of existing Zawar Cement Works (ZCW) of ZCPL, located in Gulbarga district of Karnataka.

The  aim to revive the old and closed plant, it is proposed to set a new project within existing plant premises after dismantling old plant.

 

As 0n  November 30, 2011 :  The  Project is  under  planning stage.

 

The project is coming up on within the boundary limits of 38 ha of existing Zawar Cement Works (ZCW) of ZCPL

 

About 12.5 ha of plant area will be developed under green belt.

IMPORTANT: As per the discussion we had on 18.11.2011 with  Jypee Cement Corporation Limited the project is under planning stage.

 

The project has received first level of Environment Clerance from Ministry Of Environment & Forest (MoEF).

 

The project is also awaiting  clerance from Sate Pollution Control Board.

 

 The Project   is Scheduled to be  Completed

in 2013 .

 

So, this is the RIGHT TIME to contact  and Follow Up Contractor  at following address obtain the detailed Enquiry of each product  in time and to

submit your quotation subsequently.

 

The Main Scope of Supply includes:

 

Boiler (AFBC) – For Captive power Plant

 

Rotary Klin: Rotary kiln with multistage preheater and 

precalcinator fo Clinkerisation of the raw meal.

Manufacturing Process & Raw Materials :

 

Dry process will be used for cement production.

Vertical Roller Mill will be provided for Drying and Grinding the raw materials.

Bended raw material will be fed to Pyro-Processing section (kiln) and heated at 14500C for clinker formation.  Clinker will be cooled and ground at closed circuit ball mills.

 

The raw materials required for the unit are Limestone 6.8 MTPA,  Coal 1.4 MTPA, Gypsum 0.3 MTPA and Fly ash 2.0 MTPA.

 

Limestone will to be transported through Pipe Cconveyor or Covered belt conveyor system from the Captive Bankur and Masrawada and Taranhalli mines.

 

About 1.4 MTPA of Indian coal or 0.88 MTPA of Imported coal will be used. The company has signed MOU with M/s Adani Enterprises Limited for supply of 1.4 MTPA of imported coal from South Africa and Indonesia. Gypsum will be sourced from Rajasthan and fly ash from the captive power plant and company?s own power plant.

 

In Captive Power Plant, chemical energy of coal will be converted to heat energy for steam generation which will be used to cement mechanical energy in a turbine to electrical energy.

 

Limestone Mining

Limestone mining will be carried out by Mechanized Opencast method of mining.

Mining will include the following activities:

- Removal of Over Burden

- Drilling & Blasting

- Crushing of Limestone

- Loading

- Transportation to the cement plant via Conveyor Belts

 

In Lime Stone Mines Crusher will be provided with Water Spray on the Hopper and at material transfer points.

Air Slides

Air Blasters

Clinker Grinder Unit

Grate Coolers

Vertical Roller

Ball Mills

High Efficiency Separators.

Cement Storage Silo

Packing Machine

 

Air Polution Control Equipment:

Electrostatic Precipitators (ESP) will be provided to cement mill and power plant. 

During transportation of mineral from mine to cement plant site, water will be

sprinkled on haul roads. Wet drilling will be done during dust suppression.

Water Spray will be done to control dust generated during loading, transportation,

unloading and crushing etc. 

Glass Fiber Bag House of >99.98% efficiency will be installed to limit the dust concentration within 50 mg/m3.

 

Online particulate emissions monitors will be installed for Kiln/Raw mill stack.

 

 Lime injection system will be provided to reduce SO2 pollution.

 

A well-designed burner system will be installed which limits the temperature to a reasonably low value of NOx generation.

 

All the conveyors will be provided with conveyer covers and hoods to offset any trapping of material in wind stream.

 

High efficiency reverse air jet type bag filters are considered to arrest the air borne dust at all the locations where transfer of material from one conveyor to other takes place.

 

The automatic bagging machine with bag filters will be installed for packing plant. The sprinkling of water will be done along the internal roads in the plant in order to control the dust arising due to the movement of vehicular traffic.

 

ESP of 99.95% efficiency will be installed in CPP and to cooler exhaust to control the dust emission below 50 mg/Nm3.

 

Atmospheric Fluidized Bed Combustion (AFBC) Boiler at the Captive Power Plant, to control the emissions of SO2.

 

 Low NOx burners will be installed at the Captive Power Plant to control the NOx emissions below 50 ppm.

 

Chimney of 80 Meter height will be maintained for adequate dispersion of gaseous emissions. Unloading of coal trucks will be carried out with proper care avoiding dropping of the materials from height.

The steam from the main steam header will be  taken to the

Turbo–Generators. After rotating the turbinethe exhaust steam is

condensed in the Air Cooled Condensers and the

condensed water is pumped to the De-Aerator and fed back to the boilers.

 

Cooling Tower

DG Sets :

Capacity  : 10,500 KW

(as stand by during Power Failure)

 

Air Conditioning Plant

 

Material Handling Equipment

Conveyors :

Pipe Cconveyor or Covered belt conveyor system

Crusher

Vibrating Screens

Pneumatic Conveying system

 

Other Systems

  • Fuel handling system
  • Ash handling system
  • Air Cooled Condenser
  • Fuel system

 

The following air pollution control systems/ measures are proposed in the Plant

1. All Conveyors will be completely covered with G.I. sheets to control fugitive  

    dust.

2. All bins will be totally packed and covered so that there will not be any chance   

    for dust leakage.

3. All the Dust Prone Points Material Handling systems to be connected with

    de-dusting system with bag filters.

4. All Discharge Points and Feed points, wherever the possibility of dust 

    generation is   there a de-dusting suction point will be provided to collect the dust.

5. The collected Dust from the Bag house of Steel Melting to be taken to a dust     storage bin through a Pneumatic Conveying system.

 

Water Treatment Plant

Filters,  Clarifier , DM Plant , RO Plant

Pumps Valves, Custom Pipeline Work 

Water requirement will be 6000m3/day for the integrated project.

 

Source of Water: The water requirement will be met be met from the

River Kagna flowing at 5 Km distance from the plant..

 

A  Dedicated Pipeline will be laid from River Bed to the plant for conveyance of water.

 

Details of Waste Water

No process wastewater will be generated.

 

There will be no wastewater discharge from the proposed cement plant

and 800 M3/Day  of wastewater would be generated from the CPP.

--------------------------------------------------------------------------------------

 

Effluent Treatment Plant

The effluents from the respective neutralization pits in the CPP (DM plant, blow down from steam generator) will be routed to an Effluent Treatment Plant (ETP).

 

The ETP would consists of :

1. Neutralizer,

2. Clarifloculator

3. Pressure filters and

4. Softener.

 

The sludge from the Clarifloculator is routed to sludge drying beds. The effluent will be subjected to tertiary treatment for 100% re-utilization.

 

Sanitary wastewater will be treated in Sewage Water Reclamation Plant (SWRP) and treated water will be used in greenbelt or in plant operations/dust suppression.

 

There will be no solid waste generation from the cement plant and the dust collected from air pollution control equipment will be 100% recycled in process. Major portion of the other solid waste (scrap from stores / workshop, sludge from septic tanks) is either re-used or sent to authorized recyclers. The fly ash generated from the CPP will be (100%) utilized in the proposed cement plant for manufacturing the Portland Pozzolona Cement (PPC). Bottom ash will be collected and used for landfill in mining area for mined out lands.

 

Material Handling Equipment – Conveyors, Screen, Crushers, Feeders, Cement Grouting Pumps, Air Pollution Control Equipments, Gear Boxes,  Cooling Tower, Blowers, E.O.T.Cranes, Hydraulic Equipments, Complete Laboratory Equipments, Water line Valve, Pump, Storage Tank, Vessels, Pipeline etc. etc.

 

Fire fighting System as per TAC norms.
 Green Belt Development plan in 33 % ie. 12.5 Ha area and a scheme for Rainwater Harvesting have to be put in place.

 Scope Of Entire Civil & Construction Work:

Construction of Office Building, Factory  Shed, Substation-Control Panel- Electrical Work,Elevators, Plumbing Work, Structural Steel Fabrication and Erection Work, Fabrication  Storage Tank, Vessels etc. etc.   

 

Companies/ General Industries/  Contractors/ Sub Contractors/ Manufacturers of Material Handling Equipment – Conveyors, Screen, Crushers, Feeders, Rotary Klin, Air Slides, Air Blasters, Heat Exchanger, Clinker Grinder Unit, Grate Coolers, High Efficiency Separators, Cement Grouting Pumps, Air Pollution Control  Equipments, Gear Boxes,  Water Treatment Plant,  Effluent Treatment Plant , Cooling Tower, Blowers, Cranes, Hydraulic Equipments, Water line Valve, Pump, Pipeline etc. etc.   may  Contact for Specified Enquiry at :

 

Jaypee Cement Corporation Limited

Sector-128, Gautam Buddha Nagar- 201304,

Uttar Pradesh, India

--------------------------------------------------------

Tel  : + 91-120-2470800/ 4609000

Fax : + 91-120-4609464

Email : jay...@jalindia.co.in

--------------------------------------------

Website : www.jalindia.com 

-----------------------------------------------------------------------------

               

         FREQUENTLY ASKED QUESTIONS  ABOUT PROJECT ENQUERIES

                   Visit : http://industrialdirectoryofindia.com/FAQ

      GET NEW PROJECTS INFORMATIONS  ONLINE  

                   

http://www.industrialdirectoryofindia.com/download

We provide information on NEW PROJECTS  such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.

                

                 with all Contact Details:

                 Company's Name

                 Address/ Phone/ Fax

                  Contact person's Name

                   E-mail Id

 

We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.

 

We make your  Bidding/MARKETING/ Sub-contracting  & Planning MORE EASY

GET YOUR COMPANY REGISTERED TODAY  AND GET ALL PROJECTS INFORMATIONS  DIRECTLY IN YOUR MAIL BOX  .

 

Visit : http://www.industrialdirectoryofindia.com/registration

 

GET ALL  BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX

------------------------------------------------------------------------------------------------------------

         

             RELEASED ANNUAL ISSUE :

      “NEW PROJECTS THIS WEEK”

Over 2250 Nos Projects Enquries Online

                Visit : http://industrialdirectoryofindia.com/annual

Nov2711.jpg
Reply all
Reply to author
Forward
0 new messages