Globus Spirits Plans to Set Up 120 KLPD Distillery with Captive Power

2,841 views
Skip to first unread message

Industrial Directory Of India

unread,
Nov 1, 2012, 2:08:57 AM11/1/12
to industrialdir...@googlegroups.com

              “New Projects This Week" 

                   RELEASED : ISSUE OCTOBER 28 /12 

              Comprising  of  Total  81 New Project Enquiries 

  with Company's Name/ Address/ Phone/ Fax/ Contact person/E-mail 
                (Published Every Week :Electronic Issue) 
          http://www.industrialdirectoryofindia.com/download

FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES

           Visit http://industrialdirectoryofindia.com/FAQ

    (Helpline : +91-900 7158 600) 

                                        

               Globus Spirits Plans to Set Up

120 KLPD Distillery with Captive Power

   ==================================             

Globus Spirits Limited  plans to set up  120 KLPD Grain Based Distillery along with  5 MW Cogeneration Power Plant (Coal/Rice Husk Based )  at Baharogora Village, District: Singhbhoom (East), Jharkhand.

It will produce ENA (Extra Neutral Alcohol), Rectified Spirit, Indian Made Foreign Liquor (IMFL) & Country Liquor (CL) in the above plant.

 

Capacity :

Distillery                   : 120 KLPD

Captive Power Plant : 5 MW

( Fuel :

Coal/Rice Husk)

Bottling Plant

 

By Prouct : CO2 will be generated during fermentation

process which will be collected and sold to authorized vendor.

 

Location : Baharogora Village,

                 District : Singhbhoom (East), Jharkhand

                    

As 0n  November 01, 2012 : The Project is under Planning Stage. 

 

The unit would come up on about 17.66 Acre of Land .

About 33% (5.8 Acre) of the area will be developed as Green Belt.

 

IMPORTANT: As per the the discussion we had

on 19.10.2012 with Globus Spirits Limited

the Project  is  under Panning Stage.

 

Pre-project activities are on.

The company is now waiting for Environmemtal clearances.

 

The project work is likely to start in

Early 2013

 

The Project   is Scheduled to be  Completed

by June 2014.

 

So, this is the RIGHT TIME to contact  and Follow Up at following address obtain the detailed Enquiry of each product  in time and to

submit your quotation subsequently.

 

The Main Scope of Supply includes:

Boiler        : 50 TPH

Fuel                   : Coal/Rice Husk

                           (300 MT/Day)

 

Stack Height           : 60 M

 

Heat Exchanger, Air Pre-Heater/ Economiser


===============================

Steam Requirement:

 

Cooking & Liquefaction               : 4.73 TPH

Multi-pressure Distillation            : 18.92 TPH

Evaporation (Integrated)              : 4.73 TPH

DWGS Drier (DDGS)                      : 13.60 TPH

Boiler Deaeration                           : 2.20 TPH

Misc Requirement                          : 0.55 TPH

-------------------------------------------------------------

               Total                        :  44.73 TPH

 

===============================

 

Raw Materials :

  1. Grains containing  62% w/w Starch        : 320 MT/day
  2. Antifoam Agent                                            : 65 kg/day
  3. Yeast (Active Dry Yeast/                          : 200 kg/day

       Distiller’s Yeast 

  1. Sulphuric Acid                                              : As required
  2. Sodium Hydroxide (Caustic)                     : 1000 kg/day

     For Main Process Plant (35% Strength)

  1. Liquefying Enzyme                                     : 129 kg/day
  2. Saccharifying Enzym                                 : 144 kg/day

 

Air Pollution Control Equipment :

Electrostatic Precipitators/ Bag Filter

 

To control the particulate emissions from Coal  Fired boiler will be controlled by ESP and emissions will be dispersed through Stack Height  of  60 Meters.

 

Steam generated from the boiler will be utilized in the generation of

5 MW Power and wil also be used for Boiler feed water heating and Distillery.

 

Flue gases after super heating the steam will pass through Economizer where they will  Pre-Heat the boiler Feed water before it enters the boiler drum. After Economizer, flue will pass through Air Pre-Heaters where they will heat the air which will be  fed to the boiler furnace for burning the fuel.

 

After Air Pre Heaters flue gases will pass through an Electro Static Precipitator where the Dust Particles will be  collected on charged electrodes. After passing through ESP, clean flue gases with dust particle concentration also known as SPM level less than 100 mg/Nm3 through a Chimney of prescribed height.

The dust will be  collected from the bottom of the ESP.

 

High pressure superheated steam from boiler will pass through a Steam Turbine and at the lower pressure will go to the condenser.

The part of the steam will be extracted from the extraction points provided on the turbine, which will be used for distillery.

 

The condensed steam will return to the steam boiler as condensate and will again be boiled as steam.

 

While passing through the turbine, the high pressure and temperature steam will rotate the turbine rotor and an Electric Alternator mounted on the same shaft.

 

Electric power will be generated by the alternator. This electric power generated will be consumed in house i.e. for running the distillery and utilities like boilers auxiliaries etc. and surplus power will be exported to the state grid.

 

Steam turbine

Coal handling system

Ash handling system

Air Cooled Condenser

Power plant stack

Single Chimney

Fuel system

Cooling Tower

 

=======================

Details of Materal Handling for Distillery:

Bucket Elevators, Vibrating  Screen,

Hammer  Mills, Screw Conveyor – 2 Nos.

 

GRAIN STORAGE : Pre-Cleaning and to store in Storage Silos.

 

GRAIN STORAGE : The grain has  to be lifted in Bucket Elevators,

screened followed by removal of stones and iron matter.

 

 Cleaned Grains are then milled using dry milling process in Hammer  Mills.

The flour is fed through the Bucket Elevators and conveyed to the Batch Tipping Machine through a Screw Conveyor.

 

The flour addition is metered through the Batch Tipping Machine with load cell arrangement, before  transferring the flour to the Slurry Tank through another Screw Conveyor (pre-masher) for slurry preparation  process. It is proposed to have

2 x 8 TPH (+  1 Standby option) as milling  paraphernalia for this Distillery.

=======================

 

Cooled Condenser  :

Use of Air Cooled Condenser to be used to reduce water consumption.

 

All the Conveyors will be covered with GI sheets to prevent the fugitive dust emission into the atmosphere.

 

DG set :

1250 KVA – 1 No

750 KVA  –  1 No

will be  installed for emergency power Back-up during power failure.

 

Stack Height (above roof level) : As per CPCB/SPCB norms

Pollution Control Equipment Measures : Adequate stack height/ Acoustic

 

will be  installed for emergency power Back-up during power failure:

      

Water Treatment Plant

Oxidisation Chamber, Pressure Sand Filter / IRF, R.O. Plant,

Tube Settler

Pumps Valves, Custom Pipeline Work.

 

Total water requirement for the above project will be

1650 m3/day and will be sourced from Ground Water & Recycled water.

 

Note :

Water requirement (Grain Based Plant) for first run would be 4793 m3/day, which will be reduced through recycling of 3143 m3/ Day of treated water Condensates.

 

WATER REQUIREMENT FOR GRAIN BASED OPERATION

 

PROCESS WATER IN LIQN & FERMENTATION : 730   KLD

WATER IN GRAIN                                                         : 33     KLD       :

SOFT WATER IN DISTILLATION (AFT)                            :208    KLD

DM WATER IN DISTILLATION FOR RS DILUTION            : 1170 KLD

SOFT WATER FOR CT MAKEUP                                   : 1240 KLD

DM WATER AS BOILER FEED                                      : 1102 KLD

BLENDING ( BOTTLING)                                                : 50     KLD

BOTTLE WASHINGS                                                     : 50     KLD

DOMESTIC CONSUMPTION                                           : 10     KLD

SOFT WATER FOR PUMP SEALING & VACCUM PUMP: 200 KLD

________________________________________________________

TOTAL WATER REQUIREMENT (A)       :     4793 KLD

 

           TOTAL WATER OUTPUT

THIN SLOPS                                                                 : 772   KLD

WATER IN WET CAKE (BY-PRODUCT)                          : 112   KLD        :

COOLING TOWER EVAPORATION LOSSES                  : 1240 KLD

WATER IN PRODUCT                                                    : 50     KLD

DOMESTIC CONSUMPTION                                           : 10     KLD

BOTTLE WASHING                                                       : 50     KLD      

STEAM CONDENSATE                                                  : 962   KLD        :

RECTIFIER SPENT LEES                                              : 1170 KLD

PRC+ FOC SPENT LEES                                              : 179   KLD

BOILER BLOWDOWN                                                   : 42   KLD

SEALING WATER                                                         : 200  KLD         :

FINAL PRODUCT                                                           :      6 KLD

________________________________________________________

TOTAL (B)    :     4793 KLD

 

   RECYCLING & UTILIZATION STREAM

THIN SLOPS RECYCLE TO LIQN PROCESS                  : 366    KLD

STEAM CONDENSATE RECYCLE FOR BOILER : 962   KLD        :

SPENT LEES (RECT) - COOLING TOWER MAKEUP       : 234   KLD

SPENT LEES (RECT) FOR RS DILUTION                        : 936   KLD

SPENT LEES PRC+FOC TO LIQ                                    : 179   KLD

PUMP SEALING WATER                                               : 180   KLD       

PROCESS CONDENSATE                                             : 286   KLD        :

________________________________________________________

Total Recycling of water per day (C) : 3143 KLD

 

TOTAL FRESH WATER INPUT   (A- C)  :  1650 KLD

* Water requirement for first run would be 4793 m3/day

 

        Water Requirement Summary

FRESH WATER REQUIREMENT FOR DISTILLERY                 : 1190    KLD

ADDITIONAL WATER FOR POWER PLANT CT MAKE UP     360    KLD   :

FOR BLENDING AND BOTTLING (INCLUDING WASHING)   : 100   KLD

________________________________________________________

TOTAL            :     1650 KLD

 

Effluent Treatment Plant

The plant washing of will be fed to clarifier.

The overflow from clarifier & the NF Reject will be taken to the collection tank for proper mixing. Effluent from the collection tank will be pumped to aeration.

 

The stream from clarifier will be feed to in Anaerobic Treatment followed by separator the sludge is separated and will be sent to equalization tank.

 

In this process the bacteria is responsible for digestion  process.

The bacteria take upon organic content of wastewater to metabolize it and

to produce biogas and are collected at the top.

 

The an-aerobically digested effluent is collected and sent to aeration tank. An aeration system consisting of surface  aeration system shall be used to provide oxygen to  bacteria. The microorganisms degrade soluble organics aerobically.

 

The mixed effluent from aeration tanks is then  sent to Chlorination.

 

Chlorine dose will adjusted to maintain the residual chlorine concentration.

 

The treated waste water will further be subjected to de-chlorination.

The chlorinated waste water will then pump to multi grade filter followed by

Activated Carbon Filter where suspended solids are  removed. Finally the treated  water shall be stored in sump and shall be further  used for Gardening, Ash conditioned and plant washing etc.

 

The sludge after treatment shall be further used  as manure. Minor quantity of Biogas generation from Treatment will be vented to atmosphere.

 

Other Equipments:

Material Handling Equipment : Conveyor, Hydraulic Equipment/Cranes

 DG Set, Air Compressor. DC/VFD Drive, Gear Box, Insulation, Valves, Pipes & Tubes, Cables, Automatic Weighing Machines for Bulk & Liquid Materials. Straight Line Steam Tunnel, Pneumatic Piston Filler, Pressure Filler,Storage Tank, Cooling Tower/ Plant, Air Conditioning Plant, Complete Laboratory Equipments  etc

 

Fire Fighting System shall be as per the TAC Norms and cover all areas where  alcohol is produced, handled and stored.

 

Provision of Foam System for Fire Fighting to control fire from the alcohol storage tank.

 

Green Belt Development plan in 33 % area 

(Approx. 5.8 Acre Acres) and a scheme for Rainwater Harvesting have to be put in place.

 

Scope Of Entire Civil & Construction Work:

Construction of Office Building, Factory  Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication  Storage Tank, Vessels etc. etc.   

 

Companies/ General Industries/  Contractors/ Sub Contractors/ Manufacturers of Boiler, Material Handling Equipment , Water Treatment Plant, Effluent Treatment Plant, Air Pollution Control  Equipments, Cooling Tower, Blowers, Cranes, Hydraulic Equipments, Water line Valve, Pump, Pipeline etc. related to Distillery Plant   may  Contact for Specified Enquiry at :

 

Globus Spirits Ltd

F-0, Ground Floor,The Mira Corporate Suites

Plot No. 1 & 2, Ishwar Nagar,

Mathura Road, New Delhi 110065, Delhi, India

----------------------------------------------------------------

Tel          : + 91-11-66424600

Fax         :  + 91-11-66424629

Email      :    corpo...@globusgroup.in 

Website :     www.globusspirits.com

 

*****************************            

        

FREQUENTLY ASKED QUESTIONS  ABOUT PROJECT ENQUERIES

                  Visit : http://industrialdirectoryofindia.com/FAQ

      GET NEW PROJECTS INFORMATIONS  ONLINE                     

                  

           http://www.industrialdirectoryofindia.com/download

We provide information on NEW PROJECTS  such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.

                

                 with all Contact Details:

                 Company's Name

                 Address/ Phone/ Fax

                  Contact person's Name

                  E-mail Id

 

We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.

 

We make your  Bidding/MARKETING/ Sub-contracting  & Planning MORE EASY

GET YOUR COMPANY REGISTERED TODAY  AND GET ALL PROJECTS INFORMATIONS  DIRECTLY IN YOUR MAIL BOX  .

 

Visit : http://www.industrialdirectoryofindia.com/registration

 

GET ALL  BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX

------------------------------------------------------------------------------------------------------------

         

             RELEASED ANNUAL ISSUE :

        “NEW PROJECTS THIS WEEK”

Oct2812.jpg
Reply all
Reply to author
Forward
0 new messages