                    RELEASED : ISSUE JANUARY 02 / 11 

              Comprising  of  Total  60 New Project Enquiries 

  with Company's Name/ Address/ Phone/ Fax/ Contact person/E-mail 
                (Published Every Week :Electronic Issue) 
          http://www.industrialdirectoryofindia.com/download

FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES

           Visit http://industrialdirectoryofindia.com/FAQ

      ( Helpline : +91-900 7158 600)

   

     KVK Nilachal Setting Up 350 MW

        Coal Based Power Plant 

   ( Updation : Refer Our Previous Report on  28.10.2010)  

                                      

KVK Nilachal Power Private Limited (A group company of KVK Energy & Infrastructure Pvt. Ltd) is  setting up  350 MW (Phase-I) Coal based Power Plant  in Kandarei Village, Cuttack District in Orissa.

 

 

Capacity :

Power Plant  : 1 X 350 MW (Phase-I)

                        3 X 350 MW (Phase-II)

                    

 Location :  

Kandarei Village, Cuttack District,Orissa.

               ,     

As 0n  January 06, 2011 : The Project is  has done the financial closure.

 

The unit would come up on about 938 Acres of Land .

 

IMPORTANT: As per the discussion we had on 03.01.2011 with  KVK Nilachal Power Private Limited  the Project Work has started which is at Preliminarily Stage Only.

 

The entire Project is coming up on about  938 Acres of Land .

 

Out of 938 Acres of Land, Main Plant will be in 250 Acres, Coal Storage is in 208 Acres, Ash Disposal is in 200 Acres, Raw Water Reservior is in 56 Acres , Railway Sliding in 24 Acres,  Green Belt in 200 Acres.

 

For Phase –I , The project work is expected to be started From  April, 2011 .

 

So, this is the RIGHT TIME to contact  and Follow Up at following address obtain the detailed Enquiry of each product  in time and to

submit your quotation subsequently.

 

The Project  Work ( Phase-I)  is Scheduled to be  Completed by by September 2012 .

(Phase-II is targeted by by March, 2013)


On completion of both phases, KVK Nilachal will be the largest power plant in the Group’s portfolio.

 

The Main Scope of Supply includes:

Boiler : Fuel : Coal fired

Heat Exchanger, Air Pre- Heater/ Economiser

 

Turbine

 

The heat energy will be generated  in the boiler  and then converting heat

energy generated in the Boiler into mechanical energy in the turbine and further converting this mechanical energy generated in the turbine into electrical energy in the alternator. Coal will be used as fuel in the boiler.

 

Fuel Requirement : Phase –I  : 1.91 MTPA of Coal

                              Phase –II : 5.75 MTPA of Coal

 

Air Pollution Control Equipment :

Electrostatic Precipitators/ Bag Filters/ Dust Suppression System

 

Total 4 nos. of High Efficiency Electro Static Precipitators (ESP) each with 6 fields (Five fields working & one standby) will be provided to bring down the Particulate emission in the exhaust gas to less than 100 mg/Nm3.

 

Dust Suppression System like fog type and water spray system will be

installed in the material unloading areas like fog type and water spray system will be

installed in the material unloading areas

 

Cooling Tower

 

Water Treatment Plant

Filters, DM Plant, Clarifier/ Deselination Plant (Sea Water Treatment) etc,etc

Pumps Valves, Custom Pipeline Work

The water required for the entire project will be 1,10,400 Cum/day (45 Cusecs) :

 

Cooling Towers make-up                96360 Cum/Day

DM water for Boilers Make-up         3840 Cum/Day

DM plant regeneration                      360 Cum/Day

Clarifier sludge loss                        1440 Cum/Day

Service Water                                1800 Cum/Day

AC & Vent.                                            6000 Cum/Day

Filter backwash                                480 Cum/Day

Domestic (Plant & Colony)                 120 Cum/Day

----------------------------------------------------------------

                                                Total 1,10,400 Cum/Day

The water required for the project will be met from Mahanadi River.

 

A dedicated Pipeline of 12 Kms. will be laid from the river bed to the plant site.


Effluent  Treatment Plant:

Trade Effluent of 26,832 Cum/day will be generated  from

1. Cooling Towers blowdown        19,968 Cum/Day

2 .Boilers blowdown                       2688  Cum/Day

3 .D.M. plant regeneration water   360   Cum/Day

4 .Service water                              1800  Cum/Day

5. Clarifer Sludge                                 1440  Cum/Day

6. Filter backwash                            480  Cum/Day

7. Sanitary Waste water                  96   Cum/Day

     (Plant & Colony)

------------------------------------------------------------

                                                Total 26,832 Cum/Day

 

 

 Other Equipments :

Material Handling Equipment : Conveyor, Screen, Crushers/ Hammer Mill, Bucket Elevators, Hydraulic Equipment/Cranes.

 

All the Conveyors will be covered with GI sheets to prevent the fugitive dust emission into the atmosphere.

 

DG Set, Air Compressor. Gear Box, Insulation, Valves, Pipes & Tubes, Cables, Automatic Weighing Machines for Bulk & Liquid Materials. Pressure Filler, Storage Tank, Cooling Tower/ Plant,

Air Conditioning Plant,

Complete Laboratory Equipments  etc

 

Fire Fighting System shall be as per the TAC Norms.

 

Green Belt Development plan in 200 Acres area Rain water harvesting pits will be constructed to harvest the roof top water inconsultation with State Ground Water Board.

 

Scope Of Entire Civil & Construction Work:

Construction of Office Building, Factory  Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication  Storage Tank, Vessels etc. etc.   

 

Companies/ General Industries/  Contractors/ Sub Contractors/ Manufacturers of Boiler, Material Handling Equipment , Water Treatment Plant, Effluent Treatment Plant, Air Pollution Control  Equipments, Cooling Tower, Blowers, Cranes, Hydraulic Equipments, Water line Valve, Pump, Pipeline etc. related to Power Plant   may  Contact for Specified Enquiry at :

 KVK Nilachal Power Private Limited

A Group Of :

KVK Energy &  Infrastructure Pvt. Ltd.

3rd Floor, Navabharat Chambers

Rajbhavan Road

Hyderabad - 500 082. India

----------------------------------

Phone: +91 40 23403589, 23403360

Fax    : +91 40 23409789

 

 -----------------------------------------------------------------------------

                       

FREQUENTLY ASKED QUESTIONS  ABOUT PROJECT ENQUERIES

              Visit : http://industrialdirectoryofindia.com/FAQ

      GET NEW PROJECTS INFORMATIONS  ONLINE                      

                  http://www.industrialdirectoryofindia.com/download

We provide information on NEW PROJECTS  such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.

                

                 with all Contact Details:

                   Company's Name

                   Address/ Phone/ Fax

                   Contact person's Name

                    E-mail Id

 

We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.

 

We make your  Bidding/MARKETING/ Sub-contracting  & Planning MORE EASY

GET YOUR COMPANY REGISTERED TODAY  AND GET ALL PROJECTS INFORMATIONS  DIRECTLY IN YOUR MAIL BOX  .

 

Visit : http://www.industrialdirectoryofindia.com/registration

 

GET ALL  BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX

------------------------------------------------------------------------------------------------------------

         

             RELEASED ANNUAL ISSUE :

       “NEW PROJECTS THIS WEEK”

Over 2250 Nos Projects Enquries Online

                Visit : http://industrialdirectoryofindia.com/annual


Jan0211.jpg
Reply all
Reply to author
Forward
0 new messages