Lee Pharma Plans For Expansion Of its Bulk Drug Production Unit From 52.2 TPA to 492 TPA

263 views
Skip to first unread message

Industrial Directory Of India

unread,
Jan 29, 2014, 10:16:02 AM1/29/14
to industrialdir...@googlegroups.com
           "New Projects This Week" 

                   RELEASED : ISSUE JANUARY 26/14 

              Comprising  of  Total  82 New Project Enquiries 

  with Company's Name/ Address/ Phone/ Fax/ Contact person/E-mail 
                (Published Every Week :Electronic Issue) 
          http://www.industrialdirectoryofindia.com/download

FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES

           Visit http://industrialdirectoryofindia.com/FAQ

    (Helpline : +91-900 7158 600) 

 

  Lee Pharma Plans For Expansion

  Of its Bulk Drug Production Unit

     From 52.2 TPA to 492 TPA

                            

Lee Pharma Limited plans for expansion of  production capacity of its  Bulk Drug  manufacturing Unit from  52.2 TPA to 492 TPA at Gaddapotharam Village, Jinnaram Mandal in Medak District, Andhra Pradesh.

 

Capacity Expansion :  

 

Bulk Drug Manufacturing Unit 

From 52.2 Ton/Year  to 492 Ton/Year           

 

Location :    Gaddapotharam Village, Jinnaram Mandal 

                     Medak District, Andhra Pradesh 

 

**************************************

As on  January 29, 2014 : The Project is under Planning Stage .

 

Total  existing site area is  23100 Sq. Meter.

The expansion project will come up on expanded area> from  23100 Sq. Meter 

to 27092 Sq. Meter . Green Belt will be developed on 8940 Sq. Meter.

 

IMPORTANT: As per the the discussion we had

on 20.01.2014 with  Lee Pharma Limited  

the Project  is  under Panning Stage.

 

The company is waiting for Environmental Clearance.

 

The Expansion Project  is Scheduled to be  Completed

in  10 - 12 Months from the date of commencement of the project. 


-------------------------------------------------------------------------------

So, this is the RIGHT TIME to contact  and Follow Up at following address

to obtain the detailed Enquiry of each product  in time and to

submit your quotation subsequently.

 

**************************

The Main Scope of Supply includes:

Boiler 

Capacity : 6 TPH - 1 No.

Fuel   :  Coal    

Stack :  Height- 30 Meter/ Dia :600 mm

 -----------------------------------------------------------------------------------------------

Air Polution Control:

Multicyclone Separator & Bag Filter


There will be  flue gas stacks  for Boiler  which are the main emission source from the plant.

Proper Stack height and air pollution control measures ( Multicyclone Separator & Bag Filter)  will be provided in order to achieve norms prescribed by statutory authority. 


************************

Existing Status of Heating Equipment:

Presently the company is  operating  one No. of  following Capacity Boiler: 

Boiler 

Capacity : 2 TPH - 1 No.

Fuel   :  Coal

Stack :  Height- 30 Meters / Dia: 350 mm 

************************

Other Equipments:

SS Jacketed Reactor

---------------------------------------------

Glass Reaction Vessel      

--------------------------------------------

Chilling Water plant  

---------------------------------------------

Filter Drier        

-----------------------------------------------

Cooling Tower : 1500 TR           

---------------------------------------------

SOLVENT RECOVERY SYSTEM         

-------------------------------------------

DM/R.O. plant                    

----------------------------------------------

Water Softener          

---------------------------------------------

Air Compressor          

----------------------------------------------

Effluent Treatment Plant 

----------------------------------------------

Pumps                       

-----------------------------------------------------

Centrifuge

----------------------------------------------

SS & HDPE Storage Tanks      

-----------------------------------------------------

Compressor

----------------------------------------------

 

**************************

DG sets 500 KVA -  2 Nos.

Existing :  180 KVA -  1 No will be used as stand by) 


For back up in the common areas as well as for essential services

above  Two New  D.G.sets will be installed..

 

Water Treatment Plant:

 Pumps, Valves, Custom Pipeline Work, Plumbing Work

Iron Filter, ACF, DM Plant etc. 

The total  Fresh Water requirement after expansion  will be 125 m3/Day.

Total Water consumption ( with Recycled Water)  :  270 m3/Day.

(Existing Consumption : 39.5 m3/Day)

 

The Source of water will be met from Tankers.

 

Details of Water Consumption (After Expansion )

1.Domestic                                 :  19  m3/Day

2.Process Water                         : 89  m3/Day

3.Boiler                                        : 38  m3/Day

4.Cooling                                 : 90  m3/Day

5.Washing                               : 10  m3/Day

6. Garden                                   : 10  m3/Day

7. D,M, Regeneration              :  03  m3/Day

8. Scrubber                               :  08  m3/Day

8. QC & RD                               :  03  m3/Day


---------------------------------------------------------------------------------------

                              Total:  270 m3/Day.

 

Effluent Treatment Plant:

Capacity : 150 m3/ Day

 (Total Industrial Waste Water : 148 m3/ Day)


The Company will have a full pledged Effluent Treatment Plant (ETP) to treat

the effluent as per the norms.


FLOW CHART FOR EFFLUENT TREATMENT

HTDS/HCOD : Collection > Equalization & neutralization >

Stripper > MEE > ATFD > TSDF

MEE Condensate will be Reused


LTDS/LCOD :Collection> ETP(Biological Treatment) > Sand

Filter > Carbon Filter >Booster pump to

Membrane Filter set > RO Plant > RO Reject to

MEE RO Permeate to Reused.

 

 Other Equipments:

Dosing Systems, Heat Exchangers, Ball Mills, Drum Mixers, Agitators, Pulverizes, Dryers, Solvent Calibration Tank, S S Reaction Vessel  with Stirrer, Gear & Elec. Motor, Holding Vessel, Automatic Filling, Pluging & Capping Machine, Patent Automatic Liquid Filling / Weighing  Machine, AIR Scrubber with hoodes, Hot Water Bath, Semi Automatic Box Strapping Machine,  Heat Shrink Wrapping Machine, Induction Sealing Machine, Water Pumps, Chemical Pumps, Storage Tanks, Water & Acid line Valves, Control Vales, Cooling Towers, Custom Pipeline Work.

 

Ventilation & Exhaust System

Complete Laboratory Equipments

Fire fighting System as per TAC norms,

 

Green Belt Development plan in 33 % area and a scheme for Rainwater Harvesting have to be put in place.

                                         

Scope Of Entire Civil & Construction Work:

Construction of Office Building, Factory  Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication  Storage Tank, Vessels etc. etc.   

 

Companies/ General Industries/ Manufacturers /  Contractors/ Sub Contractors/ Manufacturers of Chemical Plant & Machineries, Water &  Effluent  Treatment Plant , Fire Fighting Equipments, Air-conditioning, Boilers, Air Pollution Control Equipment, Pumps, Motors Valves For Acid line, Pipeline Jobs  for the above project  may  Contact for etc.etc. may  Contact for Specified Enquiry at  :

 

Lee Pharma Limited    

SY. No. : 257 & 258/1, Door No : 11-6/56-C, 

Opp : IDPL Factory Moosapet, Balanagar ( Post )

Hyderabad – 500 037,Andhra Pradesh, India 

---------------------------------------------------

Tel :  +   91- 40-66170334 /35/36

Fax : +   91- 40-66170330

Email      :  in...@leepharma.com /purc...@leepharma.com

Website  :  www.leepharma.com

 

**************************************               

         FREQUENTLY ASKED QUESTIONS  ABOUT PROJECT ENQUERIES

                   Visit : http://industrialdirectoryofindia.com/FAQ

      GET NEW PROJECTS INFORMATIONS  ONLINE   

                    http://www.industrialdirectoryofindia.com/download

We provide information on NEW PROJECTS  such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.

                

                 with all Contact Details:

                 Company's Name

                 Address/ Phone/ Fax

                 Contact person's Name

                 E-mail Id

 

We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.

 

We make your  Bidding/MARKETING/ Sub-contracting  & Planning MORE EASY

GET YOUR COMPANY REGISTERED TODAY  AND GET ALL PROJECTS INFORMATIONS  DIRECTLY IN YOUR MAIL BOX  .

 

Visit : http://www.industrialdirectoryofindia.com/registration

 

GET ALL  BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX

------------------------------------------------------------------------------------------------------------

         

             RELEASED ANNUAL ISSUE :

      “NEW PROJECTS THIS WEEK”

  Over 2250 Nos Projects Enquries Online

 


Jan2614.jpg
Reply all
Reply to author
Forward
0 new messages