Archit Organosys Plans To Set Up
4750 Ton/Month Chemical Unit
Archit Organosys Ltd. plans to set up a Synthetic Organic Chemical Production Unit
having Capacity of 4750 Ton/Month at Kala Talav Village in Bhavnagar District , Gujarat.
Capacity : 4750 Ton/Month
Following Products will be manufactured in the proposed plant :
-------------------------------------------------------
Total : 4750 Ton/Month
Location : Kala Talav Village, Bhavnagar District , Gujarat.
**************************************
As on December 04, 2013 : The Project is under Planning Stage .
Total site area (undeveloped) is 30,040.75 Sq. Meter.
An area of about 33% of the total project area will be developed with green belt.
IMPORTANT: As per the discussion we had on 27.11.2013 with
Archit Organosys Ltd. the Project is under Panning Stage.
The company is waiting for Environmental Clearance.
The Project is Scheduled to be Completed in 12 Months
From the date of commencement of the project work.
-------------------------------------------------------------------------------
So, this is the RIGHT TIME to contact and Follow Up at following address
to obtain the detailed Enquiry of each product in time and to
submit your quotation subsequently.
**************************
The Main Scope of Supply includes:
Boiler : 2 TPH - 1 No.
Fuel : Coal/ White Coal (78.75 Ton/Month)
Stack : 30 Meter (Dia : 500 mm)
Heat Exchangers, Air Pre-heater/Economiser).
Air Pollution Control Equipment :
Multi Cyclone Dust Collector
The plant shall be provided with Multi cyclone Dust Collector
for collection of the fly ash that would be produced from the Process of coal combustion in Boiler Furnace.
To control emissions from Process Vents adequate Scrubber will be installed.
MANUFACTURING PROCESS
Chlorinated Paraffin Wax (CPW)
• Paraffin wax is melted in a Vessel provided with steam jacket. Wax become matter wax & that charged to anther Glass Line Vessel for steam heating Now any chlorine gas is introduced to the bottom of vessel at proper regulated rate.
• The reaction temp is maintained at 100 C for 18 to 20 hrs. Librated HCl vapor is absorbed in water in packed absorption column. For stabilizer added before packing the product.
Mono Chloro Acetic Acid (MCAA)
• Charge Acetic Acid in the reactor. Heat the reactor to 100 °C and start chlorination. Acetic acid is converted into Mono chloro Acetic Acid with suitable catalyst.
• During the process HCl gas is also generated, which is scrubbed by scrubber and dissolved in water to get 30% HCl liquor.
• After completion of reaction, mass is transferred in bowls for crystallization where natural followed by induced cooling takes place. After about 70 hrs pure MCA crystals are recovered. After centrifuging MCA product is ready for packing.
****************************************************
Sodium Mono Chloro Acetic Acid (SMCA)
• Charge MCA and Soda Ash in the reactor for blending. Then the mass is ready called Sodium Mono Chloro Acetate. This is taken for the drying and packing. The Final product is ready to dispatch.
****************************************************
Tri Chloro Acetyl Chloride (TCAC)
• The reacted mass already taken into the TCAC reactor is further cooled down. After cooling down the mass at the desired temperature gradual addition of sulphur mono chloride is carried out and chlorination is carried out. On the completion of the reaction crude product is formed. The vent gases evolved during the process sent to the scrubbing system.
• The crude product formed in TCAC is distilled out and the vapors of the final products are condensed and collected in
separate in separate drums and then packed for dispatch.
Other Equipments:
SS Reactor
---------------------------------------------
Glass Line Vessel
---------------------------------------------
Autoclave
---------------------------------------------
Receiver S.S. tank
---------------------------------------------
Storage Tank
--------------------------------------------
Safety valve
--------------------------------------------
Chilling plant & pump
---------------------------------------------
Cooling Tower with pump
---------------------------------------------
Drum Lifter
----------------------------------------------
Valve
---------------------------------------------
Pipe line :
---------------------------------------------
Fire hydrant
---------------------------------------------
Reactor with distillation condenser
---------------------------------------------
Acetic acid pump
**************************
DG sets :
500 KVA - 1 No.
For back up in the common areas as well as for essential services
above Four D.G.sets will be installed..
Water Treatment Plant:
The total water requirement will be 2, 48,620 Liter/ Day
(Fresh : 2, 27,520 Liter/Day + Domestic : 13,500 Liter/Day + Gardening :7,600 Liter/Day)
Details of Water Consumption ( Industrial)
Total : 2, 54,000 Liter/ Day
(Fresh : 2, 27,520 Liter/Day + Recycled : 26,000 Liter/Day + 480 Liter/Day from condensate)
1. Process Washing : 200 Liter/Day
2. Cooling Tower (Make-up) : 7,800 Liter/Day
3. Boiler : 36,000 Liter/Day
4. Scrubbing : 2,10,000 Liter/day
---------------------------------------------------------------------------------------
Total: 2,54,000 Liter/ Day
Details of Waste Water Generation
1. Process Washing : 200 Liter/Day
2. Cooling Tower : 800 Liter/Day
3. Boiler Blow Down : 200 Liter/Day
4. Scrubbing ....------------------------------------------- --------------------------------------------
Total: 1200 Liter/ Day
Effluent Treatment Plant:
The industry will generate 1200 Liter/Day of effluent.
The proposed ETP will be well designed to treat 1200 Liter/Day Effluent.
What ever the pollution load will generatemanaged by the industry and facility provided.
ETP will have one Primary Settling Tank
Total effluent generation will be 1200 Liter/Day i.e. Effluent load will be 50 liter/hr.
approximately.
RETENTION TIME IN PST : Volume of PST 1800 Liter
Effluent load 50 Liter/hr.
= 36 Hours (SO IT IS ADEQUATE)
Other Equipments:
Dosing Systems, Heat Exchangers, Ball Mills, Drum Mixers, Agitators, Pulverizes, Dryers, Solvent Calibration Tank, S S Reaction Vessel with Stirrer, Gear & Elec. Motor, Holding Vessel, Automatic Filling, Pluging & Capping Machine, Patent Automatic Liquid Filling / Weighing Machine, AIR Scrubber with hoodes, Hot Water Bath, Semi Automatic Box Strapping Machine, Heat Shrink Wrapping Machine, Induction Sealing Machine, Water Pumps, Chemical Pumps, Storage Tanks, Water & Acid line Valves, Control Vales, Cooling Towers, Custom Pipeline Work.
Ventilation & Exhaust System
Complete Laboratory Equipments
Fire fighting System as per TAC norms,
Green Belt Development plan in 33% area and a scheme for Rainwater Harvesting have to be put in place.
Scope Of Entire Civil & Construction Work:
Construction of Office Building, Factory Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication Storage Tank, Vessels etc. etc.
Companies/ General Industries/ Manufacturers / Contractors/ Sub Contractors/ Manufacturers of Chemical Plant & Machineries, Water & Effluent Treatment Plant , Fire Fighting Equipments, Air-conditioning, Boilers, Air Pollution Control Equipment, Pumps, Motors Valves For Acid line, Pipeline Jobs for the above project may Contact for etc.etc. may Contact for Specified Enquiry at :
Archit Organosys Ltd.
Prop: Shri Chlochem Limited (Archit GROUP)
4th Floor, Smit Complex, B/H, Navrangpura Post Office
Navrangpura, Ahmedabad – 380 009, Gujarat, India
---------------------------------------------------
Tel : + 91-79-26563035/ 26448514
Fax : + 91-79-26564964
Email : exp...@chlochem.com
Website : www.chlochem.com
**************************************
FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES
Visit : http://industrialdirectoryofindia.com/FAQ
GET NEW PROJECTS INFORMATIONS ONLINE
http://www.industrialdirectoryofindia.com/download
We provide information on NEW PROJECTS such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.
with all Contact Details:
Company's Name
Address/ Phone/ Fax
Contact person's Name
E-mail Id
We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.
We make your Bidding/MARKETING/ Sub-contracting & Planning MORE EASY
GET YOUR COMPANY REGISTERED TODAY AND GET ALL PROJECTS INFORMATIONS DIRECTLY IN YOUR MAIL BOX .
Visit : http://www.industrialdirectoryofindia.com/registration
GET ALL BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX
------------------------------------------------------------------------------------------------------------
RELEASED ANNUAL ISSUE :
“NEW PROJECTS THIS WEEK”
Over 2250 Nos Projects Enquries Online