RELEASED : ISSUE May 20 /12
Comprising of Total 82 New Project Enquiries
with Company's Name/ Address/ Phone/ Fax/ Contact person/E-mail
(Published Every Week :Electronic Issue)
http://www.industrialdirectoryofindia.com/download
FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES
Visit : http://industrialdirectoryofindia.com/FAQ
(Helpline : +91-900 7158 600)
Brahmaputra Biochem Plans to Set Up
60 KLPD Distillery with 2 MW CPP
==================================
(Update: Ref Our Earlier Report on 28.03.2011 & 11.08.2011)
Brahmaputra Biochem Private Limited plans to
set up 60,000 Litre/Day Grain Based Distillery along with
2MW Captive Power Plant in Kamrup District, Assam.
It will manufacture ENA (Extra Neutral Alcohol) / RS (Rectified Spirit).
Capacity :
Distillery : 60,000 Litre/Day
Captive Power Plant : 2MW
Bottling plant :Installation of bottling plant
for 6000 Cases/Day for
Country Liquor.
Distillery will be operated for 330 days per annum.
Location: Choygaon Industrial Growth Centre
Village 2 No. Jambari,Tehsil Choygaon Kamrup District, Assam
As 0n May 22, 2012 :
(Please also refer our Earlier Report on 28.03.2011 & 11.08.2011)
The the civil work has commenced.
The unit would come up on about 10 Acres of Land .
Greenbelt will be developed in 33 % (3.3)Acres) of the area.
IMPORTANT:
1. Our Report on 11.08.2011:
As per the discussion we had on 08.08.2011 with Brahmaputra Biochem Private Limited, the Project still is under Panning Stage.
The project has received first level of Environment Clerance from Ministry Of Environment & Forest (MoEF).
The project is also awaiting clerance from Sate Pollution Control Board.
The project work is expected to start from
October, 2011.
The Project is Scheduled to be Completed
by August, 2012 .
So, this is the RIGHT TIME to contact and Follow Up at following address obtain the detailed Enquiry of each product in time and to
submit your quotation subsequently.
2. Update as on 22.05.2012:
The project is delayed by about 4-5 Months.
The Civil Work has commenced .
The Project is Scheduled to be Completed by July, 2013 .
*****************************
The Main Scope of Supply includes:
Boiler : 25 TPH
Fuel : Rice Husk/ Coal
Rice Husk : 157 MTPD or
Coal : 100 MTPD
Stack Height : 43 M
Heat Exchanger, Air Pre- Heater/ Economiser
Raw Material :
Broken Rice : 161 MTPD
Sulphuric acid : 30 Kg/Day
Antifoam : 30 Kg/KL
Yeast and Biocides, Alpha amylase and Glucomylase will also be used as raw materials.
Steam turbine
Coal handling system
Ash handling system
Air Cooled Condenser
Power plant stack
Single Chimney
Fuel system
Cooling Tower
Cooled Condenser :
Use of Air Cooled Condenser to be used to reduce water consumption.
All the Conveyors will be covered with GI sheets to prevent the fugitive dust emission into the atmosphere.
Air Pollution Control Equipment :
Multi Cyclone & Bag Filter
To control the particulate emissions from the Rice Husk /Coal Fired Boiler
(25 TPH) will be controlled by Multi-cyclone followed by bag filter alongwith stack height (43 m) will be provided (within 100 mg/m3 ).
2MW Power and wil also be used for Boiler feed water heating and Distillery.
Flue gases after super heating the steam will pass through Economizer where they will Pre-Heat the boiler Feed water before it enters the boiler drum. After Economizer, flue will pass through Air Pre-Heaters where they will heat the air which will be fed to the boiler furnace for burning the fuel.
After Air Pre Heaters flue gases will pass through Multi Cyclone & Bag Filter where the Dust Particles will be collected on charged electrodes. After passing through Multi Cyclone & Bag Filter, clean flue gases with dust particle concentration also known as SPM level less than 100 mg/Nm3 through a Chimney of prescribed height.
High pressure superheated steam from boiler will pass through a Steam Turbine and at the lower pressure will go to the condenser.
The part of the steam will be extracted from the extraction points provided on the turbine, which will be used for distillery.
The condensed steam will return to the steam boiler as condensate and will again be boiled as steam.
While passing through the turbine, the high pressure and temperature steam will rotate the turbine rotor and an Electric Alternator mounted on the same shaft.
Electric power will be generated by the alternator. This electric power generated will be consumed in house i.e. for running the distillery and utilities like boilers auxiliaries etc.
DG set : Total power requirement will be 1995 KW which will be met
from Captive Power Plant (2.0 MW).
DG sets : 1000 KVA - 2 Nos
(ie. 2X 1000KVA)
will be installed for emergency power
Back-up during power failure:
Fuel : HSD
Pollution Control by Adequate stack height/ Acoustic Enclosure
*****************************
Water Treatment Plant :
(Oxidisation Chamber, , IRF, Activated Carbon Filter, DM Plant,
R.O. Plant etc.)
Pumps Valves, Custom Pipeline Work
The fresh water requirement of this project is estimated as 761 m3/day.
But while obtaining first level of Environment Clerance from Ministry Of Environment & Forest the Committee restricted to 600 m3/day
to achieve 10 Kl/Kl.
Effluent Treatment Plant
Spent wash (555 MT) will be taken to Centrifuge Decanter, where the suspended solids will be removed as wet coke.
Thin slop (180 MT) will be recycled.
Balance (271 MT) thin slop will be evaporated to 28-30% w/w syrup. Thick syrup (36MT) will be mixed with wet cake and dried as DDGS and sold as cattle feed
DM Plant rejects and Cooling Tower discharge will be treated and reused. Sewage will be treated in septic tank and disposed through soak pit.
Other Equipments:
Material Handling Equipment : Conveyor, Hydraulic Equipment/Cranes,
DG Set, Air Compressor. DC/VFD Drive, Gear Box, Insulation, Valves, Pipes & Tubes, Cables, Automatic Weighing Machines for Bulk & Liquid Materials. Straight Line Steam Tunnel, Pneumatic Piston Filler, Pressure Filler,Storage Tank, Cooling Tower/ Plant, Air Conditioning Plant, Complete Laboratory Equipments etc
Fire Fighting System shall be as per the TAC Norms and cover all areas where alcohol is produced, handled and stored.
Provision of Foam System for Fire Fighting to control fire from the alcohol storage tank.
Green Belt Development plan in 33 % area
(Approx. 3.3 Acres) and a scheme for Rainwater Harvesting have to be put in place.
Scope Of Entire Civil & Construction Work:
Construction of Office Building, Factory Shed- Boiler House, Substation-Control Panel- Electrical Work, Plumbing Work, Structural Steel fabrication and Erection Work, Fabrication Storage Tank, Vessels etc. etc.
Brahmaputra Biochem Private
Limited
C - 24C Scheme, H S B House,
Bhagwan Das Road,
Jaipur 302001, Rajasthan. India
----------------------------------------------------------------
Tel: +91-141-2366928/ 2374907
---------------------------------------
E-mail : brahmaput...@gmail.com
-----------------------------------------------
Guawahi Office :
Brahmaputra Biochem Private Limited
House No. 16, Bye Lane – 2, Lahimi Nagar
Beltola, Guwahati – 781028,Assam, India
-------------------------------------------------
Plant :
Brahmaputra Biochem Private Limited
Choygaon Industrial Growth Centre
Village 2 No. Jambari,Tehsil Choygaon
Kamrup District, Assam, India
--------------------------------------------------------------------
****************************
FREQUENTLY ASKED QUESTIONS ABOUT PROJECT ENQUERIES
Visit : http://industrialdirectoryofindia.com/FAQ
GET NEW PROJECTS INFORMATIONS ONLINE
http://www.industrialdirectoryofindia.com/download
We provide information on NEW PROJECTS such as Automobiles,Aviation, Breweries & Distilleries, Biotech,Banking & Finance, Cement,Construction & Machineries,Chemicals,Coal,Dairy,Defence, Drugs & Pharmaceuticals, Engineering, Food Processing,Packaging,Fertilizers, Hospitality & Healthcare,HRD Hotels & Restaurant, Infrastructure, IT, ITES, BPO,KPO, Iron & Steel,Logistic. Metallurgy, Minerals, Mining,Material Handling & Warehousing, Oil & Natural Gas, Paper, Passenger Cars, Polymers, Petrolium,Ports,Pipelines, Power & Transmission, Real Estate,Resort & Tourism,Renewable Energy,Rural Development, Roads & Highways, SEZ, EPZ, Shopping Plazas, Storage & Distribution, Sugar, Textiles,Tyres, Refineries, Transport Equiments, Valves, Vegetable Oils, Water & Waste Water Treatment and many other Industries.
with all Contact Details:
Company's Name
Address/ Phone/ Fax
Contact person's Name
E-mail Id
We provide the information of Projects for various stages right from Land Acquisition, Starting Of Civil Work, Vendor Registration & Material Procurement etc. etc. to completion.
We make your Bidding/MARKETING/ Sub-contracting & Planning MORE EASY
GET YOUR COMPANY REGISTERED TODAY AND GET ALL PROJECTS INFORMATIONS DIRECTLY IN YOUR MAIL BOX .
Visit : http://www.industrialdirectoryofindia.com/registration
GET ALL BUYING LEADS FOR YOUR PRODUCT DIRECTLY IN YOUR MAIL BOX
------------------------------------------------------------------------------------------------------------
Over 2250 Nos Projects Enquries Online
Visit : http://industrialdirectoryofindia.com/annual