Hi,
I am a student working on the water use of thermal power plants. I cannot find a way to set up the annual operation hours and it shows in the 'GET RESULTS: PLANT PERFORMANCE' as a result. Could anyone help me with how to set up annual operation hours or other parameters associated with it?
Thank you!
Karen Kietzke, Research Programmer, IECM, CMU
unread,
Oct 1, 2020, 2:47:54 PM10/1/20
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to IECM User Forum
Annual Operating Hours is calculated based on the Capacity Factor found on the SET PARAMETERS: Overall Plant: Performance input screen. A Capacity Factor of 100% means the plant is operating 24/7.