Costing Production Light Manufacturing

225 views
Skip to first unread message

V. Susanto

unread,
Apr 27, 2015, 12:35:19 AM4/27/15
to idem...@googlegroups.com
Dear iDempiere Community,

Currently I testing Light Manufacturing in iDempiere, and got some case, could you please help and advice for the case below.

I added a product P10202000102J PC Flake Lempeng with BOM (included machine inside the BOM), then I created a production order

Production Order # 1000022
Value of component production for each product
Production Line No End Product Product Code Product Name Planned Quantity Quantity Used Movement Quantity Price List Standard Average Invoice Price Description
1000022 100 Yes P10202000102J PC Flake Lempeng 5,00   5, 0, 0 Price Not defined yet
1000022 110 No AA0102000002 PC Lempeng 5,21 5,21 -5,21 30,00 30,23076935 Raw Material
1000022 130 No AW0103000101 Debu giling PC 0,15 -0,15 0,15 0,00 0 By Product
1000022 150 No M0120001100 Machines Crusher PC. 0,0165 0,0165 -0,0165 5,00 0 Machine Usage & rate

When production completed, then check production journal created as listed below

Account Accounted Debit Accounted Credit Product Account Date PostingType
58600_Rate Variance 157,50 0,00 P10202000102J_PC Flake Lempeng Brna  04/17/2015 Actual
14130_Work In Process 0,00 0,00 P10202000102J_PC Flake Lempeng Brna  04/17/2015 Actual
14120_Product asset 0,00 157,50 AA0102000002_PC Lempeng Brna  04/17/2015 Actual
14120_Product asset 0,00 0,00 AW0103000101_Debu giling PC 04/17/2015 Actual
14120_Product asset 0,00 0,00 M0120001100_Mesin Crusher PC. 04/17/2015 Actual
  157,50 157,50      

The Posted production journal should contain as listed below if standard price used.

Account Accounted Debit Accounted Credit Product Account Date PostingType Quantity Used
58600_Rate Variance P10202000102J_PC Flake Lempeng 42111 Actual
14130_Work In Process 157,5025806 P10202000102J_PC Flake Lempeng 42111 Actual
14120_Product asset 157,5023083 AA0102000002_PC Lempeng 42111 Actual 5,21
14120_Product asset 0 AW0103000101_Debu giling PC 42111 Actual 0,15
14120_Product asset 0,00027225 M0120001100_Mesin Crusher PC. 42111 Actual 0,0165
157,5025806 157,5025806

Question:
  1. On accounting posted journal, seem the cost calculation for production order based on average invoice price of material (30,23076935) not price defined in the standard price list How to use standard price list for material ? or FIFO price on material usage for production order?

  2. I want to include machine usage rate in the BOM, so the hours of machine usage for the production calculated as part of production cost. to do this I configured machines in resources, and put it as a BOM of finish product, added a standard price list for machine rate.
    How to include machine's usage hour as part of production cost?
Please advice for the case above, thank you in advance.

best regards,

Susanto








Copy of Posting_20150420091307.xls

Andy Conn

unread,
Oct 31, 2016, 2:56:31 PM10/31/16
to iDempiere
Hello - currently also wrestling with this scenario. Did you find a resolution?

PShepetko

unread,
Nov 1, 2016, 1:53:32 AM11/1/16
to iDempiere
Hello,
We are using  Libero Manufacturing with Standard Costing. But you  can use my answer for Light Manufacturing too.
1) You can update Standard Cost through Price List when we will use process Standard Cost Update.
2) For  Labor and Resource ware using Resources and new Cost Elements.

Best Regards,
Peter 

понедельник, 31 октября 2016 г., 21:56:31 UTC+3 пользователь Andy Conn написал:

V. Susanto

unread,
Nov 1, 2016, 3:24:43 AM11/1/16
to iDempiere
Hi Andy,

you can follow advice from Peter.

i was wrong, i though cost definded from pricelist, actually it taken from cost field, as Peter said.
so you need to define a cost for each BOM and iDempiere will sum it all and listed on posting button.

good luck and thank you.

Susanto