If I plan a work order in idempiere, can I get a dated replenishment report (or proposed purchase orders)?
I understand manufacturing light does not give dates, just the list of what needs to be replenished. Does Libero do this, is it functional?
If the WO starts in 3 months, and raw material is very expensive and has a delivery time of 2 weeks, I do not want to order it now to optimise money flow. I need a way to see that it is not needed right now.
I saw that odoo could not do this (at least until version 6, didn't check later versions) and weberp does it, but schedules for the delivery date of the WO, which is practically useless - I need the materials at start, not at end of WO.
So I am interested whether idempiere provides this functionality.
many thanks,
Klaus