Hello!
Please resolve my doubt. Situation: i make a planing product of a table. A table has 4 legs and a countertop. This items are produced and have their own bill of material.
A table is prodused in the one workshop, but legs and a countertop are produced in the second workshop
However they have the same product category.
I make planing:
and i get three planings
but
if the planing works only for the resource i must get only one planing.
if planing works recursively i must get three planing 10 tables 40 legs and 10 countertops
Virtualy I got 10 tables 10 legs and 10 countertops
Question: how this form works?
And
![](https://groups.google.com/group/idempiere/attach/916912b1d625/Auto%20Generated%20Inline%20Image%205?part=0.5)
Where is dates from - to?
Thank you