--To view this discussion on the web visit https://groups.google.com/d/msgid/idempiere/157ccda6-ba7f-4cc1-8f39-cff581912f81%40googlegroups.com.
You received this message because you are subscribed to a topic in the Google Groups "iDempiere" group.
To unsubscribe from this topic, visit https://groups.google.com/d/topic/idempiere/MRq_Kh8_cYM/unsubscribe.
To unsubscribe from this group and all its topics, send an email to idempiere+...@googlegroups.com.
--
You received this message because you are subscribed to the Google Groups "iDempiere" group.
To unsubscribe from this group and stop receiving emails from it, send an email to idempiere+...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/idempiere/daa1b91a-82a0-49d5-8820-28bfa3ddab64%40googlegroups.com.
To unsubscribe from this group and stop receiving emails from it, send an email to idempiere+unsubscribe@googlegroups.com.
To unsubscribe from this group and stop receiving emails from it, send an email to idempiere+...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/idempiere/e2dad1df-d815-49fa-bace-64c3384587aa%40googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/idempiere/694b1273-88c5-41fb-bf70-6df2f9951174%40googlegroups.com.
Average cost and Standard cost? not sure how we would handle average cost unless you adopted costing level of 'batch and lot' ... then changed the calculation of manufacturing variances so they disappeared and got added into product cost instead.
Assume we have product A1 with a BOM consisting of Prod A2 and prod A3
we made/purchased prod A2 over a number of months and we have instances that cost us $10, $15 and $20
we purchased all the prod A3 at same time for $10
we have a single Production Order to make 10 product A1,
we now have 3 Product A1 which cost us $20, 3 which cost us $25 and 4 which cost us $30.
Product B1 has a BOM of 1 x product A1 and 1 x Product A4.
We had a Production Order for Product A4 last month and found the same varying cost outcome as for product A1 above so we have A4 items in stock costed at $40, $50 and $60.
.... now what do we want to do?
when some one asks 'what does an 'B1' cost what would we tell them?
There is a good reason why Std Cost was adopted for manufacturing...
Hi RedhuanThe key element of success of a good scheduling and then shop floor management and warehouse management is a soft link between it and the ERP.On side of ERP, Steve and Martin know very well the need and the problems, so them input is important.It is important not to mixte both sides, because on the job scheduling, FMS and WMS side it need to be highly adapted for each installation. And this must be done in fact, economical and robust way.This is not possible if you mixte both (like in libero) you need to have flexible connection and on the job scheduling, FMS/WMS side to be organised with layer, going from generic to particular.The generic is form all,particular is for a specific plant of a specific company in a specific business area.You cannot have the same systems in a plant to do beers, cosmetics, cars, military devices, electronic devices etc...But you cannot have to develop everything from scratch every time. So you must be able to highly adapt without risk to introduce bugs in the core system.On other axe the system needs to be evolutif, to enable permanent improvement. In some electronics plants like mobile phone, they have new models every 3 months. They cannot redesign the software each time.Then we must separte resource management of other (reason why you have 3 axles in CIM-OSA cube.Implement such a think is complex, but KalimaCache and JSPlugin connected with, java, android, J2EE and existing iDempiere including OSGI, make it possible for us.We just need to work together to add all our experiences and we will succeed. (I am already at the 3d generation of such system. the last one is intended to be connected to your work)André
--
You received this message because you are subscribed to the Google Groups "iDempiere" group.
To unsubscribe from this group and stop receiving emails from it, send an email to idempiere+...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/idempiere/1d353682-fceb-4d0f-8dd0-5b261f57e907%40googlegroups.com.
To unsubscribe from this group and stop receiving emails from it, send an email to idempiere+unsubscribe@googlegroups.com.
Hi RedhuanI read more deeply Steven e_mail.I agree with Steve point of view.About work in progress locator, this is include in my side, user can see, from web, mobile and/or tablet where is any work (or delivery) in progress.We can send (look at interface proposal) information about good consuption so you can update inventory in real time.We also send information when a product is done, where it goes : to warehouse or to some truck loading.We have some module to know (for just in time delivery) what is the stock in client warehouse, in truck to be deliver, and ready to be loaded. This infortions can be display on LED panels, on web and/or on tablets.In the wms side, it will be a graphical 3D vison of what parts are in each warehouse location. Warehouses can have asrs and avg connected to our system so avg and asrs can get the next place where to load and unload some parts.André