Hi folks,
The information on the NZTA web site about the P2N project is rather sketchy. For example, it does not address the Kaiwharrawharra shared path, Petone Esplanade, Dowse Interchange or lack of road shoulder at Melling. Not much on the width or path surface for the road side option along the waterfront, or details of the reclamation for the seaward side. How wide is the actual reclamation? Where is the 3m width measured, etc.
The road side option aims at a 3m width, but this will be achieved for only 80% of the length. So there will be a number of pinch points, which might make this option very unattractive.
So far 650 submissions.
Rob Napier, the AECOM project manager, is available on Friday 14th March at the AECOM office to go over the details –they have a lot more than is on the web site. If you would like to attend this meeting, please let me know, and what times would suit you on the Friday.
Tom
--
You received this message because you are subscribed to the Google Groups "Hutt Cycle Network" group.
To unsubscribe from this group and stop receiving emails from it, send an email to hutt-cycle-netw...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
My understanding is that Kaiwharrawharra section is going to be sorted with WCC/GWRC separately to the P2N project and the Esplanade is Hutt City’s issue, the others however are very relevant. I am happy to attend with you Tom - I am flexible on time on that day.
As discussed today I will develop some bullet points for next Thursday’s monthly Network meeting to form the basis for a discussion at that meeting to work up a formal Hutt Network submission. It will be bare bones bullet points as you have and others have greater knowledge. It will be a discussion starter.