Residents, 
The paving contractor finished 75% of Middle road. They will return on Monday to topcoat Cavender and then finish Middle road. The other crew will begin reclaiming on Kings Highway on Monday. The grader will continue on High street, Verney road and Birch road. Remember this is all weather dependent. 







Tyler Howe, Director of Public Works
PO Box 6
Hancock NH 03449