Residents, 
The grader will be finishing up on Eaton Road. 
The backhoe will be finishing on Shady Lane and Heading to Weston Road. 
The first week of June we rented a gravel machine to gravel the shoulders on Middle road and Cavender road. 
The paving contractor will be back in July to pave Kings Highway to Nubanusit. 
June we will be ditching on Old Dublin road from flagstone to the Harrisville town line so we can gravel it this summer. 