Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Project accounting with Gen. • Site meeting with Mike B. • Ford on-site setting up art studio in small garage. • Maui Garage Door on-site resetting small garage door. • HES on-site finishing up device installs and listing remaining material inventory needed. • Mario and team onsite installing entry nook bench at lower level. • Received additional epoxy flakes from Mike B. • Put Donnie’s contract and deposit in motion. • Hilltop on-site setting exterior tiles. • Completed mirror installs at master vanity. • Began milling Monkey Pod treads for lineal lights. • Continued roof top decking installs. • Drywall finishers complete. • Scheduled Elegant paintings return for Wed. to complete interior painting. • OAC pool meeting with Mike B. Mike Ramos and Drew. • Woodys not on-site. • EDesign not on site. Quote of the day: “Stay. Stay. Stay. Until it’s done.”
|
|||||||||||||||||