Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Confirmed details of mid level wall at pool with Hilltop. • Hilltop began flamed basalt tile install at pool mid level wall. • Received details from Drew for mid level wall at pool. • Hilltop crew on-site continuing setting tile at Hale back lanai. • Next level on-site finishing Kona stone tub shelf. • Next Level removed kitchen island counter top. • Confirmed the cut mirrors from Glass Products Hawai’i will be delivered to the site tomorrow Wed. AM. • Keith Drew on site painting spiral stair steel. • Worked with Keith Drew prepping for railing post welding to steel beams above at spiral stairs. • Worked with HES to complete prep for electrical inspection. • Maui County rough in complete inspection scheduled for tomorrow Wed. at 11:00 AM. • Received site visit from EDesign’s Josh • Edesign crew not on -site. • Drywall finishers onsite. • Woodys plumbing not on-site. • Ramos Pools continuing prepping pool and spa for coping and tile. • Continued roof top decking installs. • Site meeting with epoxy contractor Donny. • Completed prep for second round of concrete coping samples. Quote of the day: “Courtesy costs nothing, but buys everything”
|
|||||||||||||||||