Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Began draining pool water. • Installed S Steel shelf’s above kegerator at storage room. • Completed rough draft for Sept. pay app # 16. • Opened up dust fence at sewer connection for CMAC. • Scheduled site meeting with James owner of elegant painting for tomorrow 9:00 AM. • Received additional delivery for Signature Shades. • Spoke with Brad Gaul regarding his starting schedule and overall schedule. Brad to supply schedules tomorrow. • Received Smart Glass replacement panel delivery. • Completed install of Kona Bed assembly. • Completed 99% of all cabinet installs at main level. • Met with Drywall finishers to review main level finish completion. Finishers to return tomorrow Wed. • Began covering/protecting all installed cabinetry at main level. • Hilltop on-site continuing on exterior and interior floor tile setting. • Onsite meeting with Dimitri. • EDesign on site picking up sound equipment. • Received updated rooftop decking details from Drew. Quote of the day: “Hope cost nothing”
|
|||||||||||||||||