Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 11/19, 20, 21 • Aloha Friday! • Began setting interior doors, door hardware, and door magnet stops at lower level. • Woodys plumbing on site setting finish fixtures at main level, and lower level. • HES on site setting finish fixtures and electrical devices at main level and lower level. • Continued setting appliances at main level. • Set pass through fridge at main level. • Elegant Painting on-site began Drywall painting at lower level. • Drywall finishers completing lower level. • Hilltop completing tile setting at Mauka shower. • Hilltop beginning wood grain tile at master bedroom. • Hilltop began and continuing on tile set at main lanai. • Keith Drew welding treads and setting first landing at interior stairs. • Weekly project OAC and OC meetings. • Site visit from Marc Taron. • Next Level continuing on counter slab installs throughout. • Hilltop continuing install of lava rock at pool planter wall. • Hilltop completed removal of flamed basalt tile at observatory window. • Removed observatory window. • Completed demo, 9” higher re framing, and re install of observatory window. • Completed switch relocation and pick up framing at observatory. • EDesign not on-site. • Completed finish bath hardware layout with Mike B. • CMAC re mobilizing to begin final grade sets and bio retention drainage beds. Quote of the day: “What is becoming proved was once only imagined”
|
|||||||||||||||||