• CMAC on-site continuing on back drainage culvert project. • Tiki torch ditches backfilled by MTZ Landscapes. • Scheduled MTZ Landscapes for Friday rubbish removal. • Worked with Gen and Olive finalizing Pay App # 21. • Keith Drew delivering 1 of 2 elevator circular stair stringers. • Keith to deliver 2 of 2 elevator circular stair stringers tomorrow Friday. • Ramos pools continuing setting blue tile at spa interior. • HES not on-site. • Mike B. and team not on site. • Continued steel stair tread assembly attachment to concrete wall at back lanai stairs. • Continued install of glass stand offs at monkey pod interior stair treads. • Secured Haleakala toilet wall slider inspection hatch. • EDesign not on site. Quote of the day: “ Never play leap frog with a unicorn”
|
|||||||||||||||||