Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Received delivery of the Struxure Shade unit for the BBQ area. • Received delivery of the glass railing stand offs for the Monkey Pod stairs. • MTZ Landscapes mobilizing equipment to begin excavation of front underground infrastructure. • Site meeting with Tomas. • Continued install of the big garage work bench. • Continued prepping for the steel stair installs. • Ramos pools onsite. • Hilltop on-site. • Mike B. and Tygrr continuing on outside shower gate fabrications. • Began boring drain line hole at back lanai area. • HES Kamalu picking up and beginning install of the pool sub panel. Quote of the day: “Calmness is the cradle of power”
|
|||||||||||||||||