Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Received approval from Leadcors Casey Lamb for CMAC to use parking lot access to transport concrete drain inlet to back of property from parking lot.• Weekly project accounting meeting with Gen.• Received notice HECO permanent power install is scheduled for Monday 10:30 AM• Scheduled pre con permanent power install meeting with Garrett and Kamalu for Friday 7:30 to 8:00 AM.• Keith Drew on-site setting the elevator stair circular stringer.• OAC meeting with Drew and Mike B.• Ramos crew on site.• Began installing exterior shower finish hardware.• Mike B. and Andrew on site.• CMAC on site taking delivery and staging of the back culvert pipe and concrete drain inlet.• Began interior room by room post permanent electrical punch list.• Received estimate for the back upper lanai glass railing panels.Quote of the day:”The best wave of your life is still out there.”
|
|||||||||||||||||