Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Woodys on site setting finish fixtures throughout. • Elegant Painting applying primer to lower level drywall. • Elegant Painting prepping interior doors at main level. • Continued setting appliances. • Continued setting lower level doors and hardware. • Keith Drew continuing on interior stair steel work. • Hilltop setting main lanai, and master wood grain tile. • Hilltop finishing up lava rock at pool planter box wall. • Hilltop prepping exterior at observatory window for tile re application. • Received notice from Access Lifts the main elevator is on island, being delivered to the site tomorrow AM. • Next Level on site continuing prepping areas that require plumbing installs. • Dropped off coded invoices at CCR. “Quality is in the details”
|
|||||||||||||||||