Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Received permanent power from HECO!• Let there be light!• Mike B. and Tygrr on-site working on exterior shower gates.• Site visit from Loren Osborn.• Ramos crew on-site setting spa tile.• HES crew on-site commissioning electrical circuitry throughout.• Continued setting cabinetry at observatory interior.• Began setting appliances at lanai BBQ.• CMAC setting concrete drain box at back drainage rehab project.• CMAC delivering equipment to spread driveway gravel.• CMAC delivering driveway base gravel this week Wed.• Spoke with Led Cores Casey Lamb about schedule of CMAC rehabbing drainage gulch.• Began detailing outside shower barn door sliding hardware.• Reviewed Deckton stair tread mock up from Next Level.• Mike B. approved Next Levels Deckton stair mock up.• Invited Ramos Pools to Basecamp.Quote of the day:”Creativity is intelligence having fun”
|
|||||||||||||||||