Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 4/20 & 4/21 • Began site demobilization. • Scheduled off haul of office container for this week Thursday. • Epoxy floor crew completed second flack prod-cast at large garage. • Epoxy floor crew to begin bunker room this week Friday. • Picked up steel stair assembly parts from Custom Metal Creations. • Researched anchoring bolts for the steel stair plates. • Picked up 1/4” aluminum rods and spacers for the outside shower gate prototype. • Began fabrication of the Timberline Teak slates for the outside shower gate prototype. • Worked with Sturdevant on AC installs at rack room and obsevatory. • Mike B. and Tygrr on-site working on shower gate frame prototype. • Met with Keith Drew to review circular stair stringer progress and details. Keith hopes to have complete this week. • Keith Drew to deliver railing stock and reminder of the shower gate stock this week Friday. • Ramos pools onsite prepping spa and pool for tile installs. • Site meeting with Mike Ramos and Dimitri. • Received and passed Maui County Elect. pool bonding inspection. • Continued upper roof decking prep and seal. • Completed Monkey Pod interior stair assembly install. • Setting up to install second and final coat of sealer for the monkey pod stairs. Quote of the day: “Three things cannot be long hidden: the sun, the moon, and the truth”
|
|||||||||||||||||