Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Aloha Friday!! • Site meetings with CMAC to review back drainage inlet. • CMAC to modify upper portion of drain inlet box. • CMAC completing 30” back culvert pipe install, and north gulch rehab. • Provided Rick Arambulo of Woodbridge Capital Partners scope report for the 30” drainpipe install. • Ramos pools onsite setting infinity edge tile. • Ramos pools setting wiring at pool equipment bunker room. • Tomas Landscaping onsite trenching and setting main sprinkler runs and low volt runs. • Keith Drew on site continuing on elevator circular stair stringer. • Prepping steel I Beam at top of elevator to except circular stair stringer. • HES on-site. • Mike B. providing aloha Friday lunch. •’Nick and Tyger installing the last of the swing outdoor shower gates. Quote of the day: “The best way out is always through”
|
|||||||||||||||||