Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Began prepping exposed steel structure at elevator for paint. • Weekly project meeting with Gen. • Scheduled Ramos Pools to return tomorrow. • Reviewed modification to Big Ass Fan at master lanai. • HES scheduled to be ready for Maui County Elect. inspection end of day Friday. • HES scheduling Maui County Elect. inspection for the first of next week. • Hilltop on-site grouting master wall tile. • Keith Drew not on site. • EDesign not on-site. • Confirmed Woodys Plumbing will be back on site this week Thursday. • Confirmed with Interior Environments the toilet shelf’s, work bench, and Mauka closet are in production. Awaiting ETA. • Picked up additional products to complete concrete coping mock ups for approval. • Continued Monkey pod milling. • Drywall finish at Rack room, observatory, and walk in closet hidden door area in progress. • Continued roof top decking installs. • Completed mounting penetrations for outside master shower tower. Quote of the day: “The pain fades, but crossing the finish line lasts forever”
|
|||||||||||||||||