Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Aloha Friday!! • Applied epoxy primer to the elevator steel structure. • Site meeting with Woody. • Ramos Pools on site prepping pool pre coping and infinity edge details. • Site meeting with Mike Ramos defining pool coping install forming details and schedule. • HES continuing prepping for Maui County Elect. • Site visit from Marc Taron. • Site meeting with Mike B. • Reviewed epoxy samples from Donny with Mike B. • Hilltop on-site • Keith Drew not on site. • EDesign not on-site. • Woodys plumbing on-site continuing prepping the hot water tanks for install. • Continued Monkey pod milling. • Drywall finish at Rack room, observatory, stair well, and walk in closet hidden door area in progress. • Continued roof top decking installs. • Performed clean up. Quote of the day: “Nature uses symmetry as a tool, not as a rule”
|
|||||||||||||||||