Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
11/25 & 11/26 • Received delivery of the Cambridge elevator. • Inspected and staged elevator for Access Lifts. • Confirmed Access Lifts will be on-site Monday 12/1 to begin elevator install. • Elegant Painting on-site continuing on drywall painting at lower level. • Woodys Plumbing on-site continuing on finish plumbing sets. • HES on-site continuing on finish device sets. • Hilltop on-site grouting, tiling, and cleaning up. • Keith Drew continuing on main interior stairs. • Hilltop patching stucco walls at moved light sconces. • Emptied Rec Room garage. • Next level on-site setting slab counter tops throughout. • Sent off pay app # 17 for approval. • Continued on appliance sets. • Completed install of interior doors. • Spread out all bathroom finish hardware. • Performed major clean up. Quote of the day: “Gratitude is the hearts memory”
|
|||||||||||||||||