Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 2/17. 2/18 • Continued prepping elevator exterior shaft for finishes. • Site meetings with Mike B. • EDesign on-site setting finishes. • Ramos Pools onsite setting equipment at bunker room. • Elagant painting on-site applying final paint at upper level. • Signature shades onsite installing main lanai shade awning. • Sturdevant onsite setting condensers and finishes. • Hilltop on-site continuing on finish tile sets. • HES on-site setting finish through out. • Keith Drew on-site setting cable railings at roof top. • Fergusion Plumbing supply delivering subzero replacement parts for main kitchen freezer. • HECO approved permanent power application. • Completed remodel at Kona HVAC upper cabinet. • Worked with Gen on project accounting. • EDesign mirror delivery scheduled for 2/19. Quote of the day: “Fate leads the willing, and drags along the reluctant”
|
|||||||||||||||||