Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:

• CMAC on-site starting on back drainage culvert upgrades.

• Woodys plumbing on-site beginning to set gas lines for the front Tiki torches.

• Worked through front Tiki torch details.

• Ramos pools on-site setting up for spa tile.

• Continued setting observatory vanity cabinet.

• Began floor prep for observatory telescope.

• HES on-site working on pool sub panel, and blank cover plates throughout.

• Mike B. and team continuing on outside shower gate frame prep & painting.

• Received notice the Parklex order has arrived on island and will be arriving on site no later than this week Wed.

• Received the Hilti concrete bolt order for the steel stair tread attachment. 

• Wrapping up the rooftop decking sealing project.

• Completed install of the two pool water fall column structures.

Quote of the day:

“When you take time to replenish your spirit, it allows you to serve others from the overflow.”




Sent with Basecamp You can reply to this email or respond in Basecamp.
This message was sent to Alana Scott, Artie Ferreira, Bob Polasek Jr., Cody Macdonald, Don Kimball, Drew Kauffman, Genevieve Sison-Dollopac, Ikaika Reyes, John Rawson, Joshua Cardeno, Kelcey Sykes, Kristen Totah, Lovely Pascual, Marc Taron, Marlon Silloriquez, Marsha Kaleikau, Mati Stamatiou, Matt Hecox, Michelle Leatherman, Mike Bennett, Nick Ross, Roger Cabudol, and Sarah Marshall.
UnsubscribeChange your notification settings
Get the Basecamp app for iPhone or Android!
Download on the App Store Download on the Play Store
27b454f1b9c7e5d7b07d526b
Reply all
Reply to author
Forward
0 new messages