Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• CMAC on-site starting on back drainage culvert upgrades. • Woodys plumbing on-site beginning to set gas lines for the front Tiki torches. • Worked through front Tiki torch details. • Ramos pools on-site setting up for spa tile. • Continued setting observatory vanity cabinet. • Began floor prep for observatory telescope. • HES on-site working on pool sub panel, and blank cover plates throughout. • Mike B. and team continuing on outside shower gate frame prep & painting. • Received notice the Parklex order has arrived on island and will be arriving on site no later than this week Wed. • Received the Hilti concrete bolt order for the steel stair tread attachment. • Wrapping up the rooftop decking sealing project. • Completed install of the two pool water fall column structures. Quote of the day: “When you take time to replenish your spirit, it allows you to serve others from the overflow.”
|
|||||||||||||||||