Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Aloha Friday!! • CMAC continuing on utilities excavations. • Site coordination meeting with CMAC and Woodys regarding utilities/site piping installs and details. • CMAC began install of piping for roof drains and lanai drains. • Woodys scheduled to begin sewer, gas, water piping beginning of next week. • Received additional 12 yard dumpster from Waste Pro Hawai’i. • Drywall finishers on site to continuing on Fry Riglet installs and continue main level drywall finish. • Continued baseboard installs at lower level. • continued protecting tile floors at lower level. • Completed bed assembly install at Kihei bedroom. • Began bed assembly install at Mauka bedroom. • Hilltop on-site continuing on exterior and interior floor tile setting, and Hale hallway shells reef. • Continued working with Keith Drew laying out main interior stairs. • Keith to begin fabricating interior stair stringers. • Performed clean up. Quote of the day: “What stands in the way, becomes the way”
|
|||||||||||||||||