Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Black Parklex screw arriving tomorrow Thursday. • Ordered the black SS glass railing stand offs for the interior stair railing. • Picked up drill press for Mike B. and Tygrr. • Mounted TP shelf at Mauka tile wall. • Sturdevant completing install of rack room and Observatory AC systems. • Elegant painting crew now scheduled to start this week Sat. • Signature Shades crew back on site next week W-F. • Signature Shades confirmed the bbq structure has shipped. • Epoxy crew applying top coat at large garage. • Epoxy crew beginning bunker room floor this week Friday. • Completed installing monkey pod tread protection at interior stairs. • Ramos crew on-site continuing prep work for tile installs. • Continued roof top decking sealer prep and install. • Staged office container for tomorrow Thursday off haul. • Researched concrete anchor bolt options for stair assemblies. • Received notice from HECO they will be sending connection fee amount and connection date. • Began study of big garage work bench install. Quote of the day: “Pleasure in the job puts perfection in the work”
|
|||||||||||||||||