Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Began installing bathroom finish hardware at main level. • Access Lifts onsite setting up for elevator install. • Keith Drew on-site working on interior stairs and welding in hangers for elevator door headers. • Elegant painting on-site painting drywall at lower level, and finishing doors at upper level. • Began setting medicine cabinets at master bath. • Hilltop on-site working on stucco and main lanai tile set. • HES on-site setting finish devices. • Confirmed IEs shop drawings for Mauka closet side panels. • EDesign not on site. • Woodys Plumbing not on site. • Received Signature Shade Solutions delivery. • Confirmed CMAC back on-site tomorrow to complete site drainage, bio retention basins, etc. Quote of the day: “Don’t let your mind rehearse disasters that may never come”
|
|||||||||||||||||