Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • CMAC crew on-site completing utility back fill. • Access lifts crew on-site installing cargo lift. • Cargo lift rep on-site directing access lifts cargo install. • EDesign crew on-site setting led under cab lights. • HES crew on-site installing electrical fixtures • Billy Wilson Drywall crew on site finishing main level, level 5. • Hilltop crew on-site. • Elegant painting crew on-site. • Signature Shades crew onsite. • Mike B. on-site welding. • Keith’s welding on-site. • Woodys plumbing crew on-site. • Next Level granite crew onsite. • Began setting interior doors, stops, and hardware at main level. • Began staging appliances at main level. • Competed install of BBQ cabs. Quote of the day: “Let’s Go!!!”
|
|||||||||||||||||