Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• CMAC on-site continuing on back drainage culvert project. • Woodys plumbing completing setting gas lines for the front Tiki torches, setting up for inspection. • Woodys plumbing on-site tomorrow to set tiki torch bases in concrete and hook up gas line at roof top fire pit. • Ramos pools setting blue tile at spa interior. • Continued setting observatory vanity cabinet, sink, hardware, etc. • HES on-site. • Mike B. and team continuing on outside shower gate frame prep, painting and assemblies. • Received delivery of the additional Parklex panel order. • Began the steel stair tread assembly attachment to concrete wall at back lanai stairs. • Completed setting up switch remodel at upper cargo lift exterior tile wall. • EDesign on site. Quote of the day: “In the middle of every difficulty lies opportunity”
|
|||||||||||||||||