Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Completed draining pool water. • CMAC continuing on utilities excavations. • Scheduled site coordination meeting with CMAC and Woodys tomorrow 8:00 AM. • Approved James proposal of Elegant Painting to finish wood ceilings. • Elegant Painting to begin prepping and finishing wood ceilings the end of next week. • Drywall finishers on site to continuing on Fry Riglet installs and continue main level drywall finish. • Completed covering/protecting all installed cabinetry at main level. • Continued baseboard installs at lower level. • Began protecting tile floors at lower level. • Completed bed assembly install at Mauka bedroom. • Began bed assembly install at Kihei bedroom. • Hilltop on-site continuing on exterior and interior floor tile setting, and Hale hallway shells reef. • Continued working with Keith Drew laying out main interior stairs. • Spoke with Chris Cowell with Contract Hardware Supply about exterior door proposal. Chris to complete proposal tomorrow. • Completed material take offs for additional roof top decking to be quoted. • Site meeting with Chuck from Maui Plumbing Fire. Quote of the day: “Anyone who keeps the ability to see beauty never grows old”
|
|||||||||||||||||