Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Completed setting interior doors, door hardware, and door magnet stops at main level. • Woodys plumbing on site setting finish fixtures at main level. • HES on site setting finish fixtures and electrical devices at main level. • Continued setting appliances at main level. • Set pass through fridge at main level. • Elegant Painting on-site continuing on Drywall painting at main level. • Drywall finishers continuing on lower level. • Hilltop competing 95% of interior tile and grout installs. • Mike B. Completing welding at interior stair stringer's. • Discussed main kitchen island slab top/cook top redo with Mike B. • Set up meeting with Darren, Next Level Granite to discuss island slab redo. • Phone meeting with Loren Osborn. • Weekly project meeting with Gen. • Site Meeting with Mike B. and Chris. • Next Level continuing on counter slab installs throughout. • Hilltop installing lava rock at pool planter wall. • Hilltop prepping main lanai for tile install. • Hilltop setting up scaffolding and removing flamed basalt tile at observatory window. • EDesign not on-site. • Picked up the Robern medicine Cabinets from Ferguson. Quote of the day: “Walking away isn’t giving up; it’s giving yourself the space to come back stronger.”
|
|||||||||||||||||