Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Continued installing bathroom finish hardware at lower level. • Access Lifts onsite continuing on elevator install. • HES installed 60amp breaker at temp power pole for Access Lifts elevator testing. • Keith Drew on-site working on interior stair treads, and upper landing at door 220. • Elegant painting on-site sealing mahogany doors throughout, and painting lower level drywall. • Site meeting with Mike B. • Hilltop on-site working on stucco and main lanai tile set. • HES on-site setting finish devices, and light fixtures. • EDesign not on-site. • Woodys not on site. • Approved IEs pricing for Mauka closet side panels toilet paper shelf’s, and work bench. • Darren, next level on-site drilling holes for beer tap mount. • Recieved and sent HES T&M format to Mike B. • Performed concrete cut at back lower lanai slab. • Downloaded site photos to Bennett 3 shared. • Spoke with epoxy contractor, Don owner of Keolani Kreations. • Don to schedule site visit hopefully tomorrow Friday. • EDesign not on site. • Woodys Plumbing not on site. • Staged Signature Shade Solutions delivery. • CMAC continued encountering major blue rock at rear bioretention basin excavation. • Weekly OC and OAC project meeting. • Requested and recieved additional details from civil engineer Alana Scott. • Requested and received additional details from Jon Harper and Artie for the Kona bath supply air vent in upper cabinet. Quote of the day: “Progress rarely arrives fully assembled; you build it piece by piece”
|
|||||||||||||||||