Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Aloha Friday!! • Continued installing bathroom finish hardware at lower level. • Bathroom finish hardware install 90% Complete. • Access Lifts onsite continuing on elevator install, and dumb waiter finish. • Access lifts back on Monday. • Keith Drew on-site working on interior stair upper landing at door 220. • Met with Keith about additional stair scope and letting the back stairs and pool stairs out to another steel contractor. Keith do provide possible candidates. • Elegant painting on-site sealing mahogany doors throughout, and painting lower level drywall. • Site meeting with Mike B. • Hilltop on-site working on stucco and main lanai tile set. • HES on-site setting finish devices, and light fixtures. • EDesign not on-site. • Woodys not on site. • Site meeting with Darren to review all needs by months end. • Received approval on the pac S proposal for the remaining exterior doors. • Completed concrete cut at back lower lanai. • Met with epoxy contractor, Donie owner of Keolani Kreations. • Donie to provide samples. • CMAC continuing bioretention basin excavation at rear. • Completing final details of roof top furniture. Quote of the day: “If the dream scares you your on the right path”
|
|||||||||||||||||